The general contractor on the Liberty Bridge rehabilitation project is disputing the Pittsburgh Bureau of Fire’s claim that it didn’t have the proper permit to do the type of “hot work” that caused a fire that closed the bridge for 24 days last month.

Joseph B. Fay Co. also said Friday it took appropriate precautions at the construction site, including having someone on “fire watch” and had fire extinguishers and water hoses available. A Sept. 2 fire caused when hot slag fell onto plastic pipe during a Fay worker’s attempt to cut steel with a torch bent a 30-foot steel chord and caused PennDOT to close the bridge for emergency repairs.

City Fire Chief Darryl Jones said Friday the city has filed a citation against Fay for not having the hot work permit. The bureau’s investigation determined the company didn’t have anyone on fire watch, had no extinguishers or other fire suppression available and didn’t properly store or cover the pipe to keep it away from the torch activity.

“This was an accidental fire and the accident was avoidable,” Chief Jones said.

Advertise with us

The city has filed a citation against Fay with a district justice that carries a maximum $1,000 fine for the lack of a hot work permit. The chief said it is “unusual for a company the size of Fay” not to have a hot work permit, which could be used at any job the firm has in the city.

In a statement, Fay said it's records show it renewed annual permits on Dec.23 and the permits are good until Dec. 31, 2016. The company said the fire department attended an April meeting before the project began that included a review of the cutting operation and never mentioned the need for a permit.

The firm would not say specifically whether its paperwork included a permit for hot work. City Public Safety spokeswoman Emily Schaffer said the department hasn’t received anything from Fay since 2014.

Chief Jones said firefighters found no sign or extinguishers, hoses or any other fire suppression material when they arrived to fight the fire. No one was on fire watch duty, either, he said.

When the Post-Gazette visited the site of the fire five days later, workers were passing out fire extinguishers to others working near the damaged chord. Fay said fire extinguishers “are always present on the bridge” but wouldn’t say whether they were in the area when the fire occurred.

Advertise with us

As part of the $80 million rehabilitation of the bridge, crews have installed work platforms at several levels of the bridge to work immediately under the deck and lower on the steel structure. Chief Jones said the fire started when slag from steel cutting on an upper platform dropped onto a lower platform where the plastic pipe was being stored.

Fay is facing deductions from its contract known as “liquidated damages” of $213,600 for each day the bridge was closed and smaller deductions for weekends and days it was open with weight restrictions. The federal Occupational Health and Safety Administration also is investigating the blaze but results aren’t expected for several months.

PennDOT assembled a team of 16 experts to design a temporary repair and monitor the structural stability of the bridge during the 24 days it was closed. Engineers still are designing the permanent fix for the bridge.