To avoid a more disruptive permanent repair later, Liberty Bridge contractors and PennDOT opted for a more extensive temporary fix that led to the bridge being closed for 24 days, executives from Joseph B. Fay Co. said Thursday.

Speaking with reporters for the first time since the Sept. 2 fire, Fay executives said Thursday their initial recommendation called for cutting a key 30-foot steel chord bent by the heat of the fire and installing braces that would have supported the same weight as the chord. That would have allowed the bridge to open sooner than 24 days — the company couldn’t say how much sooner — but would have required another closure when it was time to make permanent repairs.

After consultation with PennDOT and a team of experts from 16 different organizations, the group agreed to make a more extensive temporary repair that involved straightening the damaged chord and using hydraulic jacks to reposition the bridge about 1 ½ inches. That took longer, but now the permanent repairs under design likely can be completed without closing the bridge again.

“It was an evolutionary process,” said Jim Wilkinson, Fay’s executive vice president. “Everybody had input. I will say there was very little disagreement… The end result was the right result.”

Advertise with us

Mr. Wilkinson and Vice President Dennis Watkins wouldn’t talk about the cause of the fire or the liquidated damages PennDOT will deduct from the company’s $80 million contract to rehabilitate the bridge. They did say no one has been disciplined and no subcontractors have been replaced as a result of the fire.

The federal Occupational Health and Safety Administration is continuing to investigate the fire, which PennDOT has said started when sparks from a steel-cutting operation ignited plastic ventilation pipe and a tarpaulin. Fay’s contract with PennDOT calls for deductions of $213,600 for each day the bridge was closed and lower amounts for days it was open with restrictions.

PennDOT is still assembling the final cost for the temporary repair, which will be part of the money deducted from Fay’s final contract payment, and “liquidated damages” for the the time the bridge was closed.

Repairing the bridge was extremely complicated, partly because experts couldn’t find another example of a bridge damaged by fire in such a manner. In addition to structural engineers and designers, the team included experts from Carnegie Mellon and Lehigh universities.

The repair process they designed required 77 steps and involved moving the bridge a quarter inch at a time with safety checks after each time it was moved. In the end, the beam and the bridge “reacted exactly the way we expected,” Mr. Watkins said.

Advertise with us

“Overall, this was a three-week process,” said Mr. Watkins. Although motorists who use the bridge probably wouldn’t agree, he said, “We actually think we got this done in a short amount of time.”

Mr. Wilkinson said the company was able to work on the far ends of the bridge during the repair and has been working 24 hours a day to get the two-year project back on schedule.