Workers appear to be one step closer to resuming construction at the new $1.5 billion UPMC Presbyterian Hospital in Oakland after the health care giant was issued an electrical permit Wednesday afternoon — but they’re still waiting on two other permits to be approved.

The city of Pittsburgh halted work at the site last Thursday, claiming some aspects of the project had begun without the required permits. The stoppage by the Department of Permits, Licenses and Inspections forced about 150 workers off the job.

Wednesday morning, Mayor Ed Gainey’s spokesperson Maria Montano posted on X that the electrical permit had been approved and “should be issued today.”

Around 3 p.m. Wednesday, UPMC spokesperson Paul Wood confirmed that UPMC did have the permit. UPMC is still waiting on two other permits to be approved and issued.

Advertise with us

“Until all permits are approved, there remains the risk that not all trade union workers could return to their jobs or that trade union workers could be sent home in the future,” Mr. Wood said.

The city said that “reviews are still ongoing” for the mechanical and suppression permits.”

“Our PLI team is in constant contact with UPMC in order to help facilitate getting workers back on the job,” Ms. Montano’s post said.

It’s currently unclear if the electrical workers will be able to resume work while UPMC waits for the issuance of the other permits.

The city declined to answer questions clarifying a timeline on the other two permits and what this issuance means for the employees who were sent home last week.

Advertise with us

Last week, Greg Bernarding, the executive business manager for the Pittsburgh Regional Building and Construction Trades Council, said he had never seen the city take such unilateral action in his 35 years as an iron worker and as a labor leader.

Allegheny County Councilman Sam DeMarco issued a statement Friday criticizing the city’s decision to stop the construction.

Mr. DeMarco said that this shutdown was an effort to pressure the health care giant into agreeing to allow the Service Employees International Union to represent its workers. The SEIU has had its sights on UPMC for years in trying to organize hourly workers at UPMC Presbyterian, the system’s flagship hospital in Oakland. However a vote for union representation among the workers has never been scheduled.

The SEIU also heavily backed Mr. Gainey’s election campaign.

“This was no sudden discovery that permits were lacking,” Mr. DeMarco’s statement said. “It was a calculated move to shut down a job creator.”

Advertise with us

Ms. Montano, who previously worked for the SEIU, pushed back on this characterization of the situation, calling it “categorically untrue,” in another post on X. “This is a limited stop work order after it was discovered during a routine inspection that work was being done without the permit to do so,” her post said.

During a City Council meeting Wednesday morning, Councilman Anthony Coghill called on Mr. Gainey’s administration to expedite the process.

“[This] affects hundreds and hundreds of people,” he said. “I’m calling on this administration to get this done and get these people back to work as fast as we can.”

Mr. DeMarco also raised concerns Wednesday afternoon that this might not be the end of this problem.

“There will be continued requests for permits as the project moves forward,” he said. “What happens with the next round? Does the city shut them down again?”

Advertise with us

He also emphasized the importance that projects “of this magnitude” stay on schedule, so as not to impact the future work that other laborers might be relying on.

“Just this round [of permitting] is going to take longer than it took Gov. Shapiro to rebuild I-95,” Mr. DeMarco said, referencing the 12-day turnaround in rebuilding a portion of the interstate that collapsed last year.