After 94 years of stretching high and long to connect Schenley Park with the neighborhood of Greenfield, the Greenfield Bridge came down this morning in a mighty cloud of dust and debris.

Though views of the implosion were limited, hundreds of residents were able to watch the event -- which went off as scheduled at 9 a.m. -- from their own homes. For safety reasons, media members set up remote-controlled cameras and then were restricted to two areas, while city officials watched from a third. Hundreds of other spectators gathered to see it from the Schenley Oval in Oakland.

There had been some concern that the weather might force a delay of the implosion, but officials decided ... and after five years of planning and three months of physical preparation, the bridge came down in a matter of seconds.

Contractors told concerned residents that the explosion would be “an air-blast,” meaning most of the vibrations would be through the air like fireworks as opposed to through the ground like an earthquake. For that reason, there was little worry about damage to nearby property.

Advertise with us

No initial reports of damage were available.

Traffic through Greenfield was restricted for the blast, until an all-clear was sounded about 15 minutes later, after workers made sure that all the electronically activated explosives had detonated.

The Greenfield Bridge, which crosses above Interstate 376 between Oakland and the Squirrel Hill Tunnel, has been closed since Oct. 19, when workers with Mosites Heavy Construction began plucking concrete and steel from its skeleton. Dykon Explosives Demolition Corp. and Kesco Inc. planted , and then, on Sunday morning, the parkway below was closed so that crews could spread 4,000 cubic yards of dirt to cushion the impact of falling debris on the highway.

The parkway could remain closed through 6 a.m. Friday as workers clear the debris, but officials are hoping the cleanup may be quicker.

Drivers leaving Downtown and headed eastbound toward Monroeville will use Exit 72A at Oakland, re-entering the highway at 78A in Wilkinsburg. Drivers coming into the city, traveling westbound from Monroeville, will exit at 78B, go through Wilkinsburg and the East End, and re-enter the highway after passing through Oakland. Local traffic can stay on the inbound parkway to Swissvale, Exit 77.

Advertise with us

The $17.5 million project is expected to culminate with a new bridge in place in about two years.

“It won’t be anything like an explosion in a movie,” Mr. Predis said. “There will be dust,” but the amount and where it travels will depend on weather conditions.

Greenfield resident Patrick Hassett, assistant director for the city’s Department of Public Works, said the biggest risk would be particles in the air, so people living within 800 feet should stay indoors during the implosion.

Major roads in Greenfield will be restricted to local traffic the morning of the implosion, Mr. Hassett said, “to keep the tourists from getting into your neighborhood streets.” Unlike some other demolition events, such as the implosion of Three Rivers Stadium, there are no prime viewing areas. Those wanting to watch will be directed to Overlook Drive in Schenley Park.

People will not be permitted within 200 feet of the bridge and authorities will be stationed on roads and riding in helicopters watching for trespassers.

Advertise with us

Residents will hear an air-horn warning three minutes before the blast. One minute before the implosion, police cars will sound their sirens. The next sound heard will be the demolition.

An all-clear will be issued and Greenfield streets reopened as soon as it is determined that all the charges exploded. That should take about 15 minutes, officials said.

The elements that could delay the implosion are weather, a computer glitch in the firing system, or intruders in the area.

Dan Majors: dmajors@post-gazette.com and 412-263-1456.