The Greenfield Bridge is less than 500 feet long and carries only about 15,000 cars a day, but it is such a key link that one city official refers to replacing it as “the mother of all projects.”
The bridge crosses above the Parkway East, connecting Alger Street in Greenfield with Schenley Park. It offers a shortcut around parkway traffic for motorists leaving Oakland and heading east.
The two-year closure for replacement is such a concern that neighborhood officials are taking extraordinary steps to work with the city on traffic concerns and to remind customers that businesses will remain open.
Pittsburgh Department of Public Works officials will hold a news conference today to outline plans for handling traffic during the $17.5 million project, which will involve imploding the existing bridge onto the Parkway East in late December. That is expected to close the interstate highway for five days between Christmas and New Year’s Day.
The bridge will close for good Friday followed by two months of demolition preparation work by Mosites Heavy Construction. On Saturday, the day after the bridge closes, there will be a neighborhood party on the Greenfield side of the span.
“The next 18 months should be very interesting,” Councilman Corey O’Connor said during a driving tour of the neighborhood last week. “This project is going to be impactful. It’s going to hurt.”
Read More
Mr. O’Connor, whose district includes Greenfield, has been working with public works, public safety and residents through the Greenfield Community Association to design alternate routes and discuss other steps to mitigate traffic problems.
Pat Hassett, the city’s assistant public works director, acknowledges that won’t be easy.
“The first two or three weeks, we are just going to sit back and watch because it’s going to be total chaos,” Mr. Hassett said. “Things will settle down over time and we will see where we can make changes to help.”
This project has put Mr. Hassett in a unique position. Not only is he overseeing the project but he also lives in Greenfield, so he’s living with it 24 hours a day.
The city will work with the Traffic 21 program at Carnegie Mellon University to use computer models to help simulate where congestion is likely to occur. It also may use mobile traffic cameras to identify congested areas and post those results on a website to help move traffic.
A big concern is motorists who try to use Greenfield to bypass Parkway East traffic from Downtown by going through the neighborhood to the Beechwood Boulevard entrance ramp just before the Squirrel Hill Tunnel. Some of that traffic uses the bridge, but motorists also could use Second Avenue to Greenfield Avenue or the Swinburne Bridge from Oakland to reach the Beechwood ramp, causing drivers to use smaller neighborhood streets if those areas become congested.
“There is really no way to find a shortcut on these neighborhood streets,” Mr. O’Connor said. “Drivers have to remember our kids run in these neighborhoods, they play in the streets.”
If neighborhood congestion becomes a problem, one possible solution would be closing the Beechwood entrance ramp to the parkway from 3 to 6 p.m. on weekdays. That was normal procedure about 30 years ago to reduce parkway congestion by eliminating the merge point before the Squirrel Hill Tunnel, allowing traffic to flow freely on the parkway.
Mr. Hassett said the city has six suggested detour routes that it will detail today. For pedestrians and bicyclists, the city is encouraging the use of Junction Hollow, where improvements have been made.
That would add 10 to 15 minutes to a walk from Greenfield to Oakland, he estimated.
The bridge was finished in 1921, among seven concrete arch bridges built in the city between 1900 and 1923. When it comes down, the only one remaining will be the Larimer Avenue Bridge over Washington Boulevard.
The condition of the bridge has been a problem for more than two decades. Nets were installed in the late 1990s to catch pieces of concrete falling onto the parkway below, followed by a metal bridge built above the parkway in 2004 to protect motorists from debris.
Mr. Hassett said the city looked at a number of options before deciding to close the bridge for replacement. Rehabilitating the existing bridge would have added only 30 years to its life span for about the same cost as replacement and the federal government likely wouldn’t have allowed building a new structure beside the existing bridge because that would have involved taking too much land in Schenley Park.
Bringing down the existing bridge will have its own problems.
The plan is to close the interstate highway for up to five days between Christmas and New Year’s Day and implode it onto a dirt pillow that will be placed there.
But that’s still two months away. The immediate concern is moving traffic at rush hour next week.
Mr. Hassett’s best advice to avoid gridlock? Plan on arriving at work early or leaving late.
“We care about the impact, but this work just has to get done,” Mr. Hassett said.
“We will try to do our best to make sure traffic can get around.”
Ed Blazina: eblazina@post-gaztte.com or 412-263-1470.