After fighting in court for more than four years for its right to build a Marcellus Shale natural gas compressor station in Cecil, MarkWest Liberty Midstream & Resources found its way back to court again this week, appealing “arbitrary and capricious” conditions that it says were placed on its approval.
Although Cecil zoning board members last month unanimously approved the construction of a new compressor station at the corner of routes 980 and 50, the company took issue with 26 conditions placed on the project by the board.
They included 24 conditions that were discussed between the parties — governing issues like noise, water quality and safety procedures — and two new ones requested by the dozens of residents who spoke out against the project at public hearings.
Those final conditions required the company to use electric, not gas, powered engines, capped the number of engines the company could use, and called for third-party testing of air quality at the site before and after operations began.
The project was approved June 15, after the township in November 2010 denied the company’s application. The issue wended its way through the courts until April, when the township exhausted all of its appeals and was ordered to approve the project.
"Although Commonwealth Court reversed the board's denial of MarkWest's application, and ordered the board to grant a special exception, the board continues to take action to block MarkWest's proposed facility — all at taxpayer's expense," the filing said.
The Denver, Colo.-based company is a partner of Range Resources and provides midstream services -- the phase between when natural gas is drilled and when it's transported through pipelines.
In its appeal filed this week in Washington County Common Pleas court, MarkWest asserts that it did not agree to the first 24 conditions approved by the board and specifically objected to the final two, among other issues.
“It is impossible, impractical and/or unreasonable for MarkWest to comply with the conditions and the conditions exceed the board’s and the township’s authority,” said the filing.
The conditions represent “an abuse of discretion” by the board, said the company, which requested the court to strike completely or modify the conditions.
Patricia McGrail, solicitor for the zoning board, said the township will respond to the appeal.
"We are hoping still to work through the issues with MarkWest and our client," said Ms. McGrail. She said lawyers from both parties will soon meet.
Company representatives could not be reached.