After more than seven hours of preparation, officials called off the implosion of the substructure of the Commercial Street Bridge Wednesday.

Officials had set up an eight-hour window for the demolition of the Parkway East Bridge, from 1 to 9 p.m. By mid-afternoon, they narrowed the time frame to 6 to 9 p.m.

But at 8:15 p.m. Wednesday, a Pittsburgh Police sergeant walked up the hill from the safety zone near the Summerset at Frick Park housing development and told the crowd of several hundred that the blast was postponed.

“I hate to be the bearer of bad news, but it’s not happening tonight,” he said as the crowd groaned. “Maybe tomorrow morning.”

Advertise with us

Richard McHale, spokesman for general contractor Fay, S&B USA Construction, who was at the construction site, said immediately after the announcement he didn’t know the exact reason for the delay.

“It’s so early, we don’t have anything yet,” he said.

In a news release, the Pennsylvania Department of Transportation said the delay was needed “while the contractor continues safety preparations.” The department said it would provide more details in the morning.

The announcement was a disappointment to the folks who lined the hillside and wall for more than a quarter mile along Parkview Boulevard overlooking the highway. They had gathered despite temperatures in the 90s to watch the demolition of the substructure of the 75-year-old bridge that sits above Frick Park just outside the outbound end of the Squirrel Hill Tunnel.

PennDOT closed the Parkway East on Friday for the demolition and replacement of the bridge, which is expected to last 25 days.

Advertise with us

The new bridge has been assembled in the park beside the old one and will be slid into place when demolition is completed and rubble is moved out of the way.

PennDOT had the new bridge built beside the one that is to be imploded so the Parkway East could be closed for only 25 days. Traditional construction would have caused serious traffic restrictions for three to four years.

Fay subcontractor Mammoet, a Netherlands-based company that specializes in moving big things, will use 42 hydraulic jacks and special skid shoes to lift and slide the new bridge into place. That is expected to happen about three feet at a time and take 24-30 hours to move it 102 feet onto the existing abutments.

At least four Mammoet workers dressed in red and yellow construction jumpsuits were at the viewing until the blast was postponed.

PennDOT also is using the highway closure to perform other work on the highway and Squirrel Hill Tunnel. For example, public safety officials had planned to conduct a safety drill to practice emergency response to an accident inside the tunnel on Thursday but that was postponed because the demolition is still pending.

The tunnel also is scheduled to be paved during the closure.