The 25-day construction dash begins Friday night on the Parkway East.
During that compressed window, construction crews plan to close the interstate highway to the 100,000 vehicles that use it every day, demolish the 846-foot Commercial Street Bridge, slide the new 22-million-pound bridge into place and install the new approaches before reopening the new structure.
Of course, the Pennsylvania Department of Transportation, general contractor Fay, S&B USA Construction and Dutch bridge-sliding specialist Mammoet have spent years developing detailed plans for the $95 million project. Once the highway closes, crews will work 24 hours a day to complete work by the Aug. 3 deadline.
Unless there are extreme conditions that jeopardize workers, weather should not be a problem until late in the project when paving will be done to tie the new bridge into the existing road.
Here's how John Myler, PennDOT's assistant district executive for construction who's overseeing the project, said they expect work to proceed:
Removing the deck
About an hour after the highway closes, Fay will have four crews at the center of the old bridge to begin removing the deck on 12-hour shifts 24 hours a day. Two crews of six to eight members each will work in each direction removing concrete and rebar so the weight on the center arch is removed in a uniform manner — "methodically," as Myler put it — to protect the stability of the structure.
Read More
Using hoe rams — a hydraulic hammer attached to an excavator — and jack hammers, they will remove the surface of the bridge and dump pieces over the side into Frick Park below. The goal is to make the pieces as small as possible so that crews in the park can move them out of the way as soon as possible.
Since the new bridge has been constructed beside the old one and time is of the essence, the plan is to move the debris aside and let it sit there. Mammoet will need a clear path for lifting the new bridge and sliding it about 102 feet into place on the existing piers.
"We can clean up afterwards," Myler said. "We've got to get enough out of the way so they can move the bridge into place."
The supports for the new bridge already have been constructed at the site, but they are buried "like a layer cake" with dirt, wooden crane mats, steel plates and fencing to protect them from damage during demolition.
In addition, crews will use heavy machinery called crushers to reduce the size of pieces being removed and to knock down parapets at each end of the bridge.
This work should take four to five days.
Implosion and sliding
Crews are expected to take the next two days to place explosive charges into pre-drilled holes in the substructure and move debris out of the way.
Residents will have at least 24 hours notice before the blast, which will be done after the deck is removed. It will have an 800-foot safety perimeter and likely take place early in the morning.
PennDOT will livestream the blast on its website and 511PA. There will be no place for visitors to watch the bridge tumble to the ground and public safety officials will use drones with thermal imaging detectors to make sure no one enters the safety zone around the time of the blast.
To prevent debris from flying around the site and potentially damaging the new bridge, much of the substructure has been wrapped in construction aprons and charges will be set to direct the debris to fall away from the new bridge.
After the blast, crews are expected to take two more days to move debris from under the bridge to make room for the new bridge to be put in place.
Then Mammoet will lead the way on the engineering marvel of lifting the fully constructed new bridge and moving it into place about three feet at a time using 42 hydraulic jacks and special skid shoes. This is expected to take 24 to 30 hours.
Reopening
From the beginning of the closure, crews also will be working to install the new approaches to the bridge. Once they secure the bridge to the abutments and the road surface is in place, traffic restrictions will be removed and the new bridge will be put into service.
After the highway reopens, crews will remove demolition debris from Frick Park. Then, they will put part of Commercial Street and the Nine Mile Run trail that had been relocated for construction back in their previous location.
Next spring, about 5,000 new trees will be planted in the park.