Now it’s time.
More than 10 years of planning, five years of discussion and two years of preliminary construction end at 9 p.m. Friday, when the Parkway East will close for 25 days for the demolition and replacement of the Commercial Street Bridge.
The first extended closure of the interstate highway in nearly 10 years is expected to send the 100,000 motorists who use the road every day scrambling to find alternatives to avoid the worst of the expected traffic jams.
After what the Pennsylvania Department of Transportation calls the most robust outreach campaign in its history, the department said public sentiment strongly favored using the innovative “accelerated bridge construction” — or ABC — process for the $95 million project, even if that involved full closure of the highway. Under ABC, contractors built the new bridge in Frick Park beside the old one and during the closure will use 42 hydraulic jacks to slide it into place after demolishing the current span.
Traditional bridge replacement would have meant at least three years of single-lane traffic in each direction.
“The amount of public outreach we did for this project has been very high and really to levels we’ve never done before, because typically we don’t close an interstate on purpose for a long period of time — usually there are emergency situations, and we’re reacting,” said John Myler, PennDOT’s assistant construction engineer for District 11 who is overseeing the project.
Read More
But with the bridge project, “We had the opportunity to get ahead of this and really inform the public and . . . minimize the impact that everybody would face with this.”

Public input also played a big role in PennDOT settling on the delta frame structure of the new bridge — it mimics the concrete arches of the current structure — and the neutral green color of the two delta supports.
Myler said the department had to start talking about replacing the 75-year-old bridge because it was reaching the end of its useful life. It is “still sound today,” but it doesn’t meet current construction standards and would have continued to deteriorate.
Bonuses for early finish
Construction to prepare for the project began in July 2024, when PennDOT lowered the exit ramp from the inbound Parkway East at Wilkinsburg by several feet. The agency wanted to use that as the primary exit for inbound traffic during the highway closure, but there wasn’t enough clearance for many tractor-trailers to use the existing ramp.
For the bridge replacement, the Parkway East will be closed between the Edgewood-Swissvale and Squirrel Hill exits, but PennDOT will encourage inbound motorists heading for Oakland or Downtown Pittsburgh to get off at Wilkinsburg. Outbound motorists heading for the eastern suburbs should get off at Oakland.
Those headed for local destinations can travel between Wilkinsburg and Swissvale and between Oakland and Squirrel Hill.
Motorists passing through Pittsburgh on their way somewhere else are advised to use the Pennsylvania Turnpike, Route 28 or Route 837 to bypass the construction area. Detours are available at the PennDOT website.
Once the highway is closed, demolition crews will take the deck off the existing bridge. Then the substructure will be demolished using explosives.
The exact date hasn’t been set yet for the implosion, but there will be a strict 800-foot safety perimeter established and there will be no viewing area. PennDOT will have a livestreaming system for those interested in watching the implosion.
After that is cleaned up, Netherlands-based Mammoet will begin moving the bridge 102 feet onto the existing abutments, using hydraulic jacks and Teflon-coated skid shoes. That is expected to take 24 to 30 hours.
Then crews will complete new approaches to the bridge from both sides.
The highway is scheduled to reopen Aug. 4 and the contractor will earn financial bonuses for finishing early and penalties for finishing late.
General contractor S&B Fay USA plans to recycle the concrete and steel rebar from the demolition.
Detours and closures
Highway motorists aren’t the only ones being inconvenienced.
The area under the bridge is part of Pittsburgh’s Swisshelm Park neighborhood, where Commercial Street and the Nine Mile Run Trail run through Frick Park. For more than six months, the road and trail have been relocated during bridge construction, and closures will last through at least Aug. 3.
After the new bridge has reopened, cleanup will continue in the park, and the road and trail will be put back in their previous locations.
Next spring, about 5,000 trees are expected to be planted in what had been the construction area.
Additional road restrictions will begin Monday night as crews continue to prepare for the bridge replacement.
There will be a single-lane closure of the highway in both directions between the Edgewood-Swissvale and Churchill interchanges from 9 p.m. to 5 a.m. through Thursday. Once the full highway closure begins on Friday, traffic will be reduced to one lane in each direction between Edgewood-Swissvale and Wilkinsburg until the new bridge opens.
Also starting at 9 p.m. Monday and lasting until early August, lane closures will occur in each direction on Route 30 (Ardmore Boulevard) between Morrow and Brinton roads and on the Boulevard of the Allies between McDevitt Place and the slip ramp from Fifth Avenue. The Boulevard of the Allies ramp to inbound Parkway East will remain open during the bridge closure.
This 25-day closure is the longest of the Parkway East anyone can remember.
The most recent closure occurred during Christmas week 2016, when Pittsburgh officials closed the highway for five days for the demolition of the Greenfield Bridge.
Staff writer Chloe Jad contributed to this report.