One day likely is too soon to reach any long-term conclusions, but Monday’s relatively light morning traffic seemed to indicate that motorists heeded the warnings to plan ahead for the first weekday closure on the Parkway East.

It seemed like many of the 100,000 motorists who normally use the Parkway East either left home early in anticipation of a traffic crunch on detour routes, took public transit or worked from home.

The highway is closed between the Edgewood-Swissvale and Squirrel Hill exits through Aug. 3 for the $95 million project to replace the 75-year-old Commercial Street Bridge. The Pennsylvania Department of Transportation is taking advantage of the closure to also perform other work on that section on the interstate highway such as paving inside the Squirrel Hill Tunnel and replacing expansion dams on the closed entrance and exit ramps at Edgewood-Swissvale.

Advertise with us

In many ways, Monday morning’s traffic seemed like a non-event. Since the pandemic and the growth of working from home, traffic on Mondays and Fridays has been lower than other weekdays.

For motorists heading into Oakland or Downtown, the recommended detour has motorists getting off the highway at Wilkinsburg and following Penn Avenue through Wilkinsburg to Fifth Avenue through Oakland and back onto the highway.

The Post-Gazette followed the detours Monday morning to gauge firsthand how traffic flowed.

Leaving from Monroeville just after 8 a.m., traffic on the Parkway East was a breeze with no backups and few other vehicles on the roadway. Taking the recommended detour at Wilkinsburg led to a little more traffic at the end of Ardmore Boulevard, where the community development corporation bought a billboard add to boost the borough that reads, “Detour traffic is temporary; tunnel traffic is forever.”

It’s unclear how well that will show off the borough because with PennDOT adjusting the timing on traffic lights there was only one stop through the business district.

Advertise with us

Things got slightly busier passing through Point Breeze, where there was a two-light delay getting through the intersection at South Dallas and Penn avenues, mostly due to motorists trying to turn left.

After turning onto Fifth Avenue, traffic flowed freely through Oakland, where Pittsburgh Regional Transit has put a monthlong hold on construction for its Bus Rapid Transit system to provide more space for traffic.

After getting back on the Parkway East near the Birmingham Bridge, the final leg to Stanwix Street in Downtown Pittsburgh was uneventful. Total travel time from Monroeville: 37 minutes.

‘Extreme Highway Makeover’

The return trip had similarly light traffic with the only holdup about six minutes at the traffic light to turn from Bouquet Street at the University of Pittsburgh’s Cathedral of Learning onto Fifth Avenue. Total return time to Monroeville was 41 minutes.

After checking social media and seeing some concern about South Braddock Avenue in Regent Square, that seemed like a place to find traffic. But it was another false alarm as traffic moved quicker than a normal midday from the Swissvale exit through the business district.

Advertise with us

PennDOT has recommended that motorists passing through the area use the Pennsylvania Turnpike from Monroeville to the Allegheny Valley exit and follow Route 28 south or the turnpike to Interstate 79 south at Warrendale to bypass the construction area. Some drivers on social media complained about traffic on Route 28 but there didn’t seem to be major delays.

Pittsburgh Regional Transit spokesman Adam Brandolph said the agency won’t have actual ridership numbers for a couple of weeks. Monitoring the agency’s park-and-ride lots showed some additional vehicles at the Hamnett lot in Swissvale, Beulah in Churchill and lots in Wilkinsburg and Monroeville.

He said the real test would come Tuesday, which normally is a higher ridership day.

“By and large, we think we have the capacity to handle more riders with existing buses,” he said.

Traditionally, PennDOT District Executive Jason Zang said at a Monday morning briefing, the first day or two of detours are the most challenging, then motorists adjust and find their best alternate route.

Advertise with us

“It usually gets better from there as people decide that they don't want to get stuck in traffic,” he said. “They will decide a different route or do something different. So hopefully, it just gets better from today.”

After a series of public meetings several years ago, PennDOT decided to build the new Commercial Street Bridge adjacent to the current one in Frick Park, close the Parkway East for 25 days during the least busy period of the year, demolish the old bridge and use 42 hydraulic jacks and skid shoes to slide the new bridge into place.

The alternative would have required lane restrictions on the highway for three to four years.

“Welcome to the first episode of ‘Extreme Highway Makeover,’ ” Zang said to open the news conference. “I don't think I could be more pleased with how things are progressing right now.”

Worker safety a focus during heat wave

Since work began Friday night, about 60% of the bridge deck had been removed as of Monday, he said, a key step in the demolition process. In the days ahead, workers will drill holes where detonators will be placed to ignite the blast.

Advertise with us

The blast needed to demolish the substructure of the bridge will take place later this week during daylight hours, although a date has not yet been set, Zang said.

Crews have begun working on the asphalt approach pavement from the bridge to the Squirrel Hill Tunnel, Zang said. New inlets, pipes and light poles are being installed on the parkway, he said, although the priority is removing the bridge deck.

Once the bridge is demolished, it will be several days until the new bridge can be installed as crews clean up the fallen debris, he said.

Among other road projects, a public safety drill will take place inside the eastbound tunnel on Thursday involving a fog machine to simulate smoke.

“We really took a look at this project and said, ‘What can we possibly do while we have the parkway shut down?’ So we're literally doing just about everything we could think of,” he said.

Advertise with us

Detour travel times have held steady around 30 minutes, said Stephanie Zolnak, PennDOT traffic engineer — about 10 minutes longer than it would normally take drivers on the interstate. The busiest rush hour times are 6 to 9 a.m. and 3 through 7 p.m., she said.

Motorists going through Wilkinsburg will have an additional challenge Monday evening while Daniels Excavating does emergency road repair work at the intersection of Penn Avenue and Center Street for Peoples Gas. The site had been blocked off before the detour began, and PennDOT determined it was too rough and needed to be repaired after motorists began using it.

The work is scheduled for 9 p.m. to 5 a.m. and flaggers will help traffic move through the area.

With a heat wave on the horizon this week, Zang said he is concerned about the weather conditions for the hundred-plus workers on the project, although he does not anticipate any delays.

“It is a flurry of work out there, something that I haven't seen in my career here, so I'm worried about their safety,” he said.

With the blast expected to go off this week, the new bridge could be put into place as early as the beginning of next week, Zang said. The project is on schedule to be completed in time for reopening Aug. 3.