Timing is everything.
The Pennsylvania Department of Transportation will take advantage of the 25-day closure of the Parkway East for the replacement of the Commercial Street Bridge to perform millions of dollars in other work between Squirrel Hill and Wilkinsburg.
Work done during the closure, which will include paving in the Squirrel Hill Tunnel and painting ramp bridges at the Edgewood-Swissvale and Wilkinsburg interchanges, can be completed more quickly and eliminate lengthy traffic restrictions that would have been needed if the work were done with the highway open, officials said.
“It’s kind of being overshadowed by the Commercial Street project, but there is a lot of work that will get done during the closure,” said John Myler, PennDOT’s assistant district executive for construction who is overseeing both projects.
“When this is done and people drive through there, they will be surprised by the amount of work that we got done. This will eliminate countless restrictions on nights and weekends.”
This is no accident or happy coincidence, Myler said.
Read More
Initially, the department was considering major upgrades to the highway between the Squirrel Hill Tunnel and Churchill after it completed the $95 million project to demolish the 75-year-old Commercial Street Bridge.
Instead, the agency designed the highway improvement bids to include specific jobs to be performed during the 25 days the highway is closed.
“This was heavily planned and coordinated,” Myler said. “We decided, ‘Let’s get the project out now and get done what we can get done during the closure.’”
Public safety training exercise inside Squirrel Hill Tunnel
Trumbull Corp., which was awarded the $100 million contract and started work in March, will be ready to ramp up its work once the highway closes at 9 p.m. Friday, pending any last-minute changes to the schedule.
It is scheduled to have dozens of workers out Saturday morning removing expansion dams on closed ramps around the Edgewood-Swissvale interchange.
In addition to tunnel paving and work on ramps at Edgewood-Swissvale and at Wilkinsburg, other work set during the closure includes laying a high-friction surface at the tunnel approaches, replacing the median from the tunnel to Edgewood-Swissvale, and setting foundations for new streetlights that will be installed between the tunnel and the Pennsylvania Turnpike in Monroeville.
“It’s going to be jam-packed,” said Jason Zang, PennDOT district executive for Allegheny, Beaver and Lawrence counties. “We’re going to get as much other work done as we can during the closure.”
In addition to construction without traffic restrictions, PennDOT and public safety officials will use the lack of traffic to conduct a safety training exercise in the closed tunnel. Officials decided to schedule the training after a smoky vehicle fire inside the Pennsylvania Turnpike’s Allegheny Mountain Tunnel in early June.
“This will include crews conducting a mock multi-vehicle crash and allowing crews from the tunnels, EMS and fire to practice how to safely and efficiently respond to the incident, while managing traffic control,” PennDOT spokeswoman Yasmeen Manyisha said in an email response to questions.
How much time will work on the closed highway save on the overall project?
A similar $73 million project that began in February 2024 between Churchill and the turnpike at Monroeville will take three full construction seasons when it finishes this fall. This project, which began in March and includes more work, should be done in spring 2028, and that would have been sooner if light poles had been available.
“It’s a real benefit to do it this way,” Myler said.