For months, Pennsylvania Department of Transportation officials have been preaching for motorists to plan ahead for the 25-day closure of the Parkway East to replace the Commercial Street Bridge.
Beginning at 9 p.m. Friday, they’ll find out how many have heeded their calls to work from home, find the best recommended detour route for them around the area between Squirrel Hill and Edgewood-Swissvale, use public transit and otherwise avoid the construction site.
The highway that carries about 100,000 vehicles a day is set to close until Aug. 3 to replace the 846-foot bridge just outside the outbound Squirrel Hill Tunnel.
“We’ve had more public outreach on this project than any project in my career,” said Jason Zang, PennDOT’s district executive for Allegheny, Beaver and Lawrence counties who has been with the department since 1999. “We’re telling people to plan ahead. Know where you’re going.”
The goal: to make sure everyone is aware of what is happening and is prepared to deal with it.
This is the most extensive closure of the Parkway East since December 2015. Then it was closed for five days between Christmas and New Year’s Day for demolition of the Greenfield Bridge on the inbound side of the Squirrel Hill Tunnel.
Read More
Since last fall, PennDOT project manager John Myler and his team have spent hundred of hours meeting with neighborhood groups, businesses, and public safety officials; reams of paper have been used to print brochures for distribution through municipal buildings, libraries and the offices of elected officials; and tons of web space has been used to spread the word.
PennDOT and Pittsburgh Downtown Partnership have met with major employers in Downtown Pittsburgh to encourage them to allow workers from the eastern suburbs to work remotely as much as possible during the closure. Those who can’t work remotely are being asked to use public transit.
“Every car we can get off the road is a big help,” Zang said.
For those who have to travel during the closure, PennDOT has established recommended detour routes. Police will be stationed throughout local neighborhoods to try to keep the crush of extra traffic moving along the designated routes through Wilkinsburg, Larimer and Oakland.

Motorists are encouraged to be patient and use those routes rather than trying to find a shortcut through an unfamiliar area.
Here are the technicalities:
The first restriction began Wednesday night and will continue from 9 p.m. Thursday to 5 a.m. Friday, when traffic will be reduced to one lane outbound between the Squirrel Hill and Edgewood-Swissvale exits while crews work on median barriers.
Beginning at 9 p.m. Friday, crews will begin unveiling signs to direct trucks and most other traffic off the inbound Parkway East at Wilkinsburg. At Swissvale, barriers will be deployed to force the remaining traffic off there.
Myler said Thursday he decided not to close the highway at Wilkinsburg because there are a lot of businesses in the South Braddock Avenue corridor at the next exit, but trucks could have difficulty making the turn at that exit. Local traffic will be able to get on at Wilkinsburg and travel to Swissvale.
Most outbound traffic from Downtown Pittsburgh will be directed to get off at Oakland and the highway will be closed just before the Squirrel Hill Tunnel at the Squirrel Hill exit. Myler strongly encouraged motorists to get off at Oakland because at Squirrel Hill three lanes of traffic will merge into one lane at the exit, which could create a massive traffic jam if too many people go that way.
It could take as long as two hours for all of the restrictions to be put in place. Then, the scramble begins for crews from Fay, S&B USA Construction to begin removing the deck to prepare the bridge for demolition before the new bridge built adjacent to the old one can be moved into place.
PennDOT recommends motorists use a special page at 511pa.com for real-time traffic conditions and plan their route accordingly each time they drive.
For motorists passing through the area:
PennDOT recommends motorists heading inbound from the Monroeville area to take the Pennsylvania Turnpike to the Allegheny Valley exit and head south on Route 28 or continue to Warrendale and use Interstate 79-279 south. Another alternative is to head south on Route 48 through McKeesport to Route 837 in Duquesne and follow that into Pittsburgh’s South Side.
The reverse options are recommended for outbound traffic passing through the area.
For motorists heading into the city:
PennDOT recommends traffic getting off at Wilkinsburg follow Penn Avenue to Fifth Avenue in Larimer and Fifth Avenue through Oakland to reenter the Parkway East near the Birmingham Bridge. Pittsburgh Regional Transit has canceled work on its Bus Rapid Transit project in Oakland during the closure to allow as many lanes of traffic as possible during the highway closure. Again, outbound traffic should reverse the directions, with traffic exiting at Oakland going on Forbes Avenue to Bellefield Avenue to Fifth Avenue.
Another option is taking Route 48 south from Monroeville to Route 837 in Duquesne to the Homestead Grays Bridge and following Browns Hill Road and Beechwood Boulevard to get on the inbound Parkway East at Squirrel Hill, or continue through West Homestead to Pittsburgh’s South Side.
Pittsburgh Regional Transit:
The agency will provide its regular bus service, but it expects park-and-ride lots to fill up early. The agency looked at special service similar to what it offered during the NFL Draft in April, but with riders going to so many different locations during the closure Executive Director Katharine Kelleman said that wasn’t possible.
Many inbound routes from the east will run into the same traffic congestion until they get to Wilkinsburg, when they can take the Martin Luther King Jr. East Busway into Oakland and Downtown Pittsburgh. Anyone who rides the bus instead of driving will make the trip less congested for everyone, officials said.
Kelleman said some extra buses will be available if ridership demand makes that necessary, but she encouraged riders to be patient and allow extra time.
After living with this project for the better part of five years, Myler said he's ready to move ahead.
"It's nice to finally be at this point," he said. "Now, it's time to get the work done."