The first big disruption for the Commercial Street Bridge replacement will begin June 29, when Commercial Street/Forward Avenue and the Nine Mile Run Trail under the Parkway East bridge close for more than a month.

The Pennsylvania Department of Transportation announced Wednesday that Commercial Street/Forward Avenue, which runs through Frick Park under the bridge, will close at 7 a.m. that day between Whipple Street and Summerset Drive. The trail will close to all bicycle and pedestrian traffic between the Nine Mile Run parking lot in Swisshelm Park and the Frick Park Commercial Street parking lot in Squirrel Hill.

PennDOT said the road and trail have to be closed for safety during continuing preparatory work for the $95 million replacement of the bridge on the Parkway East just outside the outbound Squirrel Hill Tunnel.

The highway will be closed for 25 days beginning July 10 for the demolition and replacement of the bridge that carries more than 100,000 vehicles a day.

Advertise with us

Crews for Fay S&B USA have been building the new bridge next to the existing structure. After the highway is closed, the bridge will be demolished and the new bridge will be moved into place using a series of hydraulic jacks.

The street and trail are expected to remain closed for at least several days after the highway reopens while crews finish removing debris from the old bridge and restoring the condition of the street and trail.

From the Swisshelm Park side, traffic will be detoured by turning left on Whipple Street, left on Monongahela Avenue, left on South Braddock Avenue, left on Forbes Avenue and left on Beechwood Boulevard to Forward Avenue.

The route is exactly the opposite from Squirrel Hill.

Subcontractor Mammoet, a Netherlands-based company that specializes in moving big things, will be responsible for pushing the new bridge into place. The company will perform a test move of about 1 foot next week, but PennDOT said the exact day for the test hasn’t been set yet.

Advertise with us

PennDOT is encouraging as many people as possible to work from home during the closure.

Motorists who must travel during the highway closure should plan ahead, PennDOT said, and follow recommended detours to avoid the construction area.

The highway will be closed to through traffic between Oakland and Wilkinsburg, although local motorists will be able to travel short distances between Swissvale and Wilkinsburg and Oakland and Squirrel Hill.

Long-distance travelers who will just be passing through the area during the closure are encouraged to use the Pennsylvania Turnpike to go around the construction area. Local motorists going into the city will have to exit the highway at Wilkinsburg and follow Penn Avenue and Fifth Avenue to get back on the highway in Oakland.