It has been talked about for nearly five years, but with the complete closure of the Parkway East just over eight weeks away, it’s time to get serious.
The highway that carries about 100,000 vehicles a day will close for 25 days between the Edgewood-Swissvale and Squirrel Hill exits beginning July 10 for the $95 million replacement of the Commercial Street Bridge.
The Pennsylvania Department of Transportation will hold a virtual meeting from 5 to 6:30 p.m. Wednesday to discuss the detours, announce the schedule for when blasting will take place to bring down part of the existing bridge and offer recommendations on how motorists who must travel can navigate through the construction area.
PennDOT is using a unique process to replace the bridge, which is located just beyond the outbound end of the Squirrel Hill Tunnel. To avoid more than four years of closure or extreme lane limitations that would have been required for conventional bridge replacement, general contractor Fay S&B USA is building the new bridge beside the existing structure and will slide it into place after the old bridge is removed.
Still, one of the busiest highways in the region will be closed for 26 days, leaving thousands of motorists to plan around the disruption.
"You've heard me say it before, but our biggest task is for people to plan ahead: Work at home if you can, plan where you have to go and how to get there," said John Myler, PennDOT’s assistant construction engineer overseeing the project.
Read More

Myler said a key to getting the project done on time will be the quick demolition of the existing bridge. Crews will remove the deck of the bridge first, then use blasting material to take down the remaining understructure.
Blasting the entire bridge would create so much debris that it would take too long to remove it, Myler said. The anticipated blasting schedule will be part of Wednesday’s meeting.
PennDOT and the contractor also will present the preferred detours it wants drivers to use during the closure. Myler recommended motorists use the 511PA app to check conditions before each trip to gauge traffic on each detour route before they leave.
The primary recommendation is to work from home or avoid the area completely.
Those drivers just passing through the area from Monroeville are advised to take the Pennsylvania Turnpike to Harmar and use Route 28, or to Cranberry and use Interstate 279. Another alternative is to follow Route 48 south from Monroeville to Route 837 and follow that through West Mifflin into the city,
The outbound detour bypassing the city is in the opposite direction.

Motorists driving inbound to destinations in the city can stay on the Parkway East to the detour exit at Wilkinsburg, which crews lowered in the first phase of the project so all vehicles can clear the highway bridge above it. The detour uses Penn Avenue to Fifth Avenue through Oakland and back onto the Parkway East.
Inbound ramps will be closed at Churchill and Forest Hills, but local residents will be able to use the highway between Swissvale and Wilkinsburg.
Outbound traffic from Pittsburgh would get off the Parkway East at Oakland and follow Fifth Avenue to Penn Avenue through Wilkinsburg and back onto the highway.
Local traffic from Squirrel Hill headed outbound could take Beechwood Boulevard, cross the Homestead Grays Bridge and follow Route 837 to the Rankin Bridge and get back on the highway at Swissvale.
The outbound on-ramps at Bates Street and Squirrel Hill will be closed.
Meanwhile, Myler said construction remains on schedule despite some rainy weather recently. Crews have installed three of the seven sections of bridge deck and should have them all done by the first week of June.
When that work is finished, crews also will begin placing 42 hydraulic jacks at strategic places on the bridge to make the move. The jacks, about the size of an office desk, are in the process of being shipped from the Netherlands, the international headquarters of expert mover-of-large-things Mammoet.
Experts will test the system by moving the new bridge about a foot in mid-June.
The department has used accelerated construction like this on smaller bridges where the new structure was moved into position after the previous bridge was removed. But at 846 feet and 22 million pounds, Commercial Street is by far the longest and heaviest structure to be handled this way.
In previous jobs, the jacks used to move bridge components were closer to the size of a coffee pot, Myler said.
The contractor can receive a sliding bonus or penalty of up to $2.5 million if the project is completed early or runs late.
“Even for an engineer who is around this every day, this is exciting,” Myler said. “It’s going to be a fun challenge to chase.”
The online meeting is available at 5 p.m. Wednesday on the PennDOT website.