For John Myler, it’s not too early for about 100,000 motorists to start planning how they will deal with the 26-day closure of the Parkway East in July.

As the state Department of Transportation’s assistant construction engineer for this district, the impact of replacing the Commercial Street Bridge near the inbound Squirrel Hill Tunnel is on Mr. Myler’s mind every day.

The closure is nearly four months away, but the department already is advising drivers to stay away from the interstate highway during the closure and pushing alternate routes to travel between Downtown Pittsburgh and the eastern suburbs during that time.

“We’re doing everything we can to reduce the number of vehicles on the road during that time,” Mr. Myler told engineers and transportation officials last week at the annual transportation forum at University of Pittsburgh’s Swanson School of Engineering. “It’s not going to work with 100,000 vehicles still trying to use that road.”

Advertise with us

For motorists driving inbound to local destinations, the highway will be open inbound from Monroeville to Swissvale, but most traffic will be directed off the highway at Wilkinsburg. The detour uses Penn Avenue to Fifth Avenue through Oakland and back onto the Parkway East.

Inbound ramps will be closed at Churchill and Forest Hills, but local residents will be able to use the highway between Swissvale and Wilkinsburg.

For motorists just passing through the area inbound from Monroeville, PennDOT is recommending three alternate routes to avoid the highway completely:

  • Taking the Pennsylvania Turnpike to Harmar and using Route 28 to head into the city.
  • Taking the turnpike to Cranberry and using Interstate 279.
  • Following Route 48 south to Route 837 through West Mifflin. Outbound would basically be the reverse.

Going outbound from Pittsburgh, most traffic will be encouraged to get off the Parkway East at Oakland and follow Fifth Avenue to Penn Avenue through Wilkinsburg and back onto the highway.

Local traffic from Squirrel Hill could take Beechwood Boulevard, cross the Homestead Grays Bridge and follow Route 837 to the Rankin Bridge and get back on the highway at Swissvale.

Advertise with us

The outbound on-ramp at Bates Street will be closed.

“Our big motto for this is to plan ahead,” Mr. Myler said. “I want our detours to be the best routes people can use.”

Mr. Myler said that despite some rough winter weather, crews have finished installing structural steel on the replacement bridge being built next to the Commercial Street Bridge. General contractor Fay S&B USA is building the new bridge next to the existing one and plans to demolish the old bridge and slide the 22 million-pound new one into place during the closure.

“The weather was tough,” Mr. Myler said. “We did lose some days. We powered through it.”

The steel work was done a couple of weeks later than the target date of the first week in February, Mr. Myler said, but the schedule has some extra time built in so the new bridge is ready when the highway closes.

Advertise with us

As the weather improves, crews will start pouring the concrete deck so it can be done in early June.

At that time, subcontractor Mammoet, a Dutch company that specializes in moving big things, can test whether the plan to use hydraulic jacks to move the new bridge into place will work. It plans to move the bridge back and forth about a foot for the test.

When the highway closes, crews will remove the bridge deck on the old bridge and then demolish remaining substructure.

“Priority 1 is getting that structure down so we can slide the new bridge into place,” Mr. Myler said. The contractor has sliding incentives and penalties of up to $2.5 million if preparations are done early or the reopening is late.

Then comes the big move, which will be only about 1 foot an hour, almost indistinguishable as it’s happening. This will be the largest structure that PennDOT has ever moved into place like this.

“We’re definitely excited about it and looking forward to the challenge,” Mr. Myler said. “We’re very confident in our ability to get it done. That’s what Mammoet does, and they’re great at it.”