The 25-day closure of the Parkway East for the demolition and replacement of the Commercial Street Bridge will be a noisy event for residents around the site — and a traffic challenge for area motorists.
Officials from the Pennsylvania Department of Transportation and contractor Fay S&B USA gave an online overview of the project Wednesday. Fay has been building the replacement bridge adjacent to the existing structure on the outbound side of the Squirrel Hill Tunnel and will slide it into place during the closure that is set to begin July 10.
“Unfortunately, this work requires the use of tools that aren’t very quiet,” said Clint Filges, Fay’s vice president of demolition.
After taking public input on the project, PennDOT decided to proceed in this quicker way rather than using traditional methods of construction that would have taken at least four years and caused severe traffic restrictions. New information at the briefing dealt with details of demolition, which will include some blasting.
Filges said work to remove the existing bridge would begin immediately after the closure at 9 p.m. July 10. Crews will work 24 hours a day to remove the deck, he said.
Remaining arches will be demolished with explosives four to seven days into the work, Filges said. There will be an 800-foot blast area and the material will be wrapped in geotechnical material to prevent flying debris, so nearby residences should not be damaged.
Read More
The blast will sound “like a loud clap of thunder,” he said.

John Myler, PennDOT’s senior assistant construction manager, said that for safety reasons there will be no viewing area for people to watch the demolition. The agency expects to set up cameras to livestream the event on its website.
Once the bridge is down, crews will remove the debris to prepare for moving the new bridge into place. All concrete from the demolition will be recycled, officials said.
To move the new bridge, 42 hydraulic jacks will be placed on the structure. It will be moved about 100 feet into place onto new foundations that already have been installed, said Michelle Olszewski, Fay’s senior project manager.
“It’s going to be a very long day,” she said. “It should be [finished in] a day, but a very long day.”
After the new bridge is in place and the highway is reopened, crews will put Commercial Street under the bridge back in its original location. It had to be moved for construction of the new bridge.
Several thousand new trees will be planted in Frick Park under the bridge in the fall, officials said.

Myler reiterated his call for commuters — as many as100,0000 a day use the bridge daily — to work remotely during the closure. Motorists who must drive should use the 511PA app to determine the least busy detour route.
Detours send traffic through the area onto the Pennsylvania Turnpike and Route 28 or Interstate 279. Local traffic will be detoured through Wilkinsburg and Oakland.
“We cannot support those traffic numbers in a reasonable way [on local detour routes],” he said. “Any car we can get off the road will help.”
Detours routes and other information about the project can be found on PennDOT’s website.