A five-year project that’s been talked about for more than 10 years begins Monday to reduce congestion on a section of Campbells Run Road in Robinson and Collier.
The $45.8 million undertaking by Allegheny County — one of the most expensive in its history — will rebuild a 1.6-mile stretch between Keiners Lane and McMichael Road. Campbells Run is parallel to the Parkway West and is a busy business corridor with more than 50 driveways and side streets emptying onto that section of the road.
The project by Golden Triangle Construction will reconstruct the road to widen the Parkway West exit at Campbells Run to two lanes, realign the area around Boyce Road and Parkway View Drive to create a four-way intersection on Campbells Run with a traffic light, and install surface drainage and two water retention basins to get rainwater off the busy roadway.
Other work includes a two-way center turning lane and left and right turning lanes at major intersections, building nine retaining walls and installing a sidewalk on Campbells Run between Business Center Drive and Penn Center Boulevard.
The goal is to reduce traffic jams that regularly occur from 4 p.m. to 6 p.m. around the Parkway West exit on weekdays.
“We’re kind of excited to see this finally getting started,” said Frank L. Piccolino III, Robinson’s township manager. “It is a bottleneck there almost every day. This is going to be a rough couple of years, but in the end we think it will be worth it.”
Read More
Jason Molinero, the county’s deputy director of public works, said the contractor will start in the middle of the construction zone and work toward the ends.
Because of the variety of work involved, he said, the order in which it will be done is important and plays a role in why the project will take nearly five years to complete.
There will be numerous travel restrictions throughout the project, but the plan is to maintain inbound traffic at all times on Campbells Run Road along with two-way traffic between Boyce Road and the Parkway West offramp. Outbound sections of the road will be closed at times and access from crossroads will be closed at times, too.
All homes, businesses and commercial properties will remain accessible.
Mr. Molinero said the new traffic light at Boyce and Parkway View is an important element of the project because it is a natural bottleneck, with traffic trying to enter Campbells Run from either side a short distance apart. Realigning the road to create one intersection with a traffic light should help eliminate that bottleneck.
Controlling water runoff with underground drainage and two retention basins around Glass Road also will help eliminate ponding that can slow traffic, he said.
“It’s not a flood control project (to handle overflows from Campbells Run), but it will help with the water flow off of the highway,” he said.
About 3,400 feet of retaining walls will be installed for two purposes.
Four walls will be built underneath to support the road by filling in areas that got some support walls installed in 2016; five more will hold back the hillside in areas where crews will cut into them to widen the road.