Things are about to get a bit more expensive for Pittsburgh International’s airlines as the airport seeks revenue to pay for its $1.7 billion terminal that opened this week.
The airport forecasts next year’s cost per enplanement — or how much an airline pays for a boarding passenger — to be $17.64, an increase of nearly one dollar from this year’s expected $16.69. It’s an even sharper jump from 2024’s $11.95 figure and the pre-pandemic cost of $9.77 in 2019.
Cost per enplanement typically directly correlates with the number of boarding passengers. In 2020, for example, the cost per enplanement at Pittsburgh International was over $20 per passenger because there were so few travelers because of the pandemic.
However, the airport has raised its cost per enplanement in recent years to generate revenue to pay off the bonds related to the terminal project. Pittsburgh International’s partner airlines are paying the bulk of the debt through increased fees.
Airport spokesman Bob Kerlik said that Pittsburgh International was not concerned that airlines would shy away from adding new flights or pull any of their existing flights due to the increased costs. The airport has started making its debt payments, which are factored into next year’s cost per enplanement, he said.
Airport CEO Christina Cassotis shared at a board meeting on Friday that the operating budget for 2026 is $154.2 million, down slightly from this year’s $156.4 million.
Read More
That’s because the airport doesn’t need to spend as much on cleaning and maintenance going forward because the train — which until this week connected the landside and airside terminals — is shut down and the baggage system has been modernized with the opening of the new facility, she said.
Last year’s cleaning and maintenance budget was $22.245 million, compared to this year’s $19.552 million. The authority board approved the airport’s $154.2 million spending plan during its meeting.
Meanwhile, passenger traffic at the airport increased by 1.7% in October compared to 2024, from 905,000 to 920,600.
The airport has served a total of 8.3 million passengers so far this year, a decrease of 1.3% from last year’s 8.4 million. Ms. Cassotis said that the gap was “very small” and could close entirely in November and December, which are two heavy travel months.
Ms. Cassotis said that no workers died during the eight-year process of constructing the new terminal, which she credited to the airport’s partnership with the federal Occupational Safety and Health Administration, which had a team monitor the site.
Three workers lost their lives constructing the old landside building when construction materials collapsed or malfunctioned.
“We wanted to make sure that we could do everything possible to send people home every night to their families, and we’re very proud of the fact that we ran a very safe program,” Ms. Cassotis said.
Airport officials made the transition from the old terminal to the new one overnight Monday and Tuesday during an operation that went smoothly, with feedback from passengers “overwhelmingly positive,” Ms. Cassotis said.
“I am so relieved, I can’t stand it,” Ms. Cassotis said midday Tuesday, about seven hours after the terminal opened. “Now we figure out what we need to tweak in real time.”






Comments