The Monongahela Incline has reopened after being out of service since March 5, Pittsburgh Regional Transit announced Friday.
The shutdown was to make repairs to the 154-year-old incline’s electrical system, PRT said in a news release. According to PRT, a pair of resistors failed, causing the incline’s brakes to engage when they weren’t supposed to. Engineers determined the resistors were underrated for the function that was needed.
A new electrical design was approved and new parts were installed, with PRT beginning testing last weekend. PRT said the incline passed a state inspection Friday and reopened at 3 p.m.
PRT said this latest repair was under a contract from the rehabilitation project of 2022-2023 and didn’t cost any additional money.
The closure last month was the latest issue the incline has faced since reopening in March 2023 after the $8.2 million rehabilitation project. Prior to the most recent closure, the incline was out of service for more than a month due to a failure of the systems that slow the cars as they approach stations.
A committee was recently formed to address the issues. PRT said the “steering committee” will help provide more support for the aging incline.
Read More
In addition to the committee, PRT said Talson Solutions, a capital project advisory and consulting services company from Philadelphia, started an independent review of the incline’s recent contracts and current procedures to help improve its reliability, maintenance and operations.