New information about proposed ramps for I-376 and Banksville Road onto Saw Mill Run Boulevard drew attention from community members during a PennDOT public meeting.
PennDOT hosted two public meetings Thursday — chock-full of images and designs — laying out an in-depth preliminary plan for the construction of exits from the inbound Parkway and Banksville Road into Saw Mill Run Boulevard.
Currently, accident rates within this stretch of road are four times higher than the statewide average for this type of facility, Bill Gross, a project manager at HDR, said during the meeting.
This is largely caused by a weave movement created by drivers on Banksville Road crossing from the right to the left to access the Fort Pitt Tunnel while eastbound Parkway drivers are moving from the left to the right to access the exit ramps to Saw Mill Run Boulevard.
This area sees a traffic volume of more than 100,000 vehicles a day and is the most heavily traveled corridor in western Pennsylvania, according to a PennDOT release video on the project that can be found on PennDOT’s website beginning Friday.
The proposed Parkway inbound exit ramp would be located about halfway between the current Parkway Center on-ramp and the existing Banksville Road inbound merge point. It would provide inbound Parkway travelers sole access to Saw Mill Run Boulevard's northbound and southbound ramps.
A bridge would take the drivers over Banksville Road and then onto a barrier-separated connector road leading to Saw Mill Run Boulevard. The existing access from the inbound Parkway to Saw Mill Run Boulevard would be cut off by this median barrier, which would stop the dangerous weave movement.
Because of this separation, PennDOT proposed that inbound Banksville Road drivers will have access to Saw Mill Run Boulevard via a new exit ramp off Banksville Road. This would then merge with the proposed inbound Parkway exit ramp.
Where Banksville Road’s slip ramp meets with the new Parkway exit ramp, it would join into a single-lane barrier-separated road, directing motorists to the already existing ramps that are currently used to get onto Saw Mill Run Boulevard.
Mr. Gross said that PennDOT is attempting to minimize impacts on nearby properties and environmentally sensitive areas. However, he did note some locations that, at least in the preliminary stages of design, might be impacted.
Seldom Seen Greenway is one of those areas. It is considered an environmentally sensitive area and is protected under a law that provides for consideration of lands suh as parks during transportation project development.
PennDOT plans to use a section of the greenway through permanent acquisition in order to construct the project, but according to Mr. Gross, it is being considered de minimis — meaning too minor to merit consideration — as in the preliminary stages, it does not appear to affect the features that qualify the Seldom Seen Greenway for protection.
Under the protective law, the public does have an opportunity to review and comment on the effects of the project on a property.
Another environmental feature that is within the project limits is the Saw Mill Run stream and tributary, according to Mr. Gross. PennDOT plans to rehabilitate a box culvert that carries the tributary underneath the Banksville interchange.
PennDOT has also identified eight properties that will likely be impacted by the project, according to Mr. Gross. He added that seven of those properties might likely require strip takes or temporary construction easements, and one will likely require total take.
“We want to emphasize that the project design is still in its preliminary stages. Therefore, the number of properties that are ultimately impacted, and to what degree they are impacted, is still subject to significant modifications,” Mr. Gross said.
As far as traffic control, PennDOT will focus on maintaining at least two lanes of traffic in each direction on the parkway. However, there will be exceptions for occasional single-lane closures during off-peak hours.
John Zelesnak, a senior project manager at PennDOT, said that as of now, their time frame is to start construction in 2023 or 2024, and completion is scheduled for 2025 or 2026.
Community commenters during the 11:30 a.m. meeting asked questions about how the permanent and temporary takes of property will affect the individuals involved.
They also provided suggestions that the meeting’s facilitators said they would check on, including a suggestion to assign the lanes before the entrance into the Fort Pitt Tunnel to prevent drivers from veering onto the bridge.
Boyce Buchanan: bbuchanan@post-gazette.com and Twitter @BuchananBoyce.