Safety issues have again delayed the implosion of the Dooker’s Hollow Bridge, Allegheny County said in a release on Thursday.

The implosion of the bridge, which crosses over O’Connell Boulevard and connects North Braddock and East Pittsburgh, is now scheduled for 2 p.m. Saturday and will be “contingent on weather and other possible factors not further slowing placement of the explosives,” the county said.

The county said its Public Works department is working with Allison Park Contractors Inc and Demtech LLC to provide the time needed to “ensure the bridge is imploded without any issues.”

The county said the delays have largely been due to “off-and-on snow and at times windy conditions this week.”

Advertise with us

It said placement of the explosives — 96 of them — is done using a large crane and “is highly technical work.”

“Safety is our top priority,” the county said.

Until the explosives are placed on the bridge, they will be guarded 24 hours a day by contractors.

The implosion is part of an ongoing $9.95 million bridge replacement project that began on Oct. 19.