The steel superstructure of the Dooker’s Hollow Bridge between North Braddock and East Pittsburgh will come tumbling down Thursday.
Crews removed the bridge deck after it was closed for replacement in October, but Allison Park Contractors Inc. decided the rest of the structure wasn’t stable enough to finish the job safely by using cranes and other equipment. Instead, subcontractors Demtech LLC of Butler and Terra‑Mechanics Inc. of West Deer will use explosives to drop 470 tons of steel into the valley beneath the bridge at 10 a.m. Thursday.
“It became clearer once they took the deck off,” said Stephen Shanley, public works director for Allegheny County, which owns the bridge. “The contractor decided it would be easier and safer to take it down this way.”
The bridge is above O’Connell Boulevard, where the county recently bought two homes near where the rubble will fall onto timber and crane pads to prevent road damage. One occupied home cost $23,125 and the other, which was unoccupied, cost $19,175.
The county already has notified residents within 1,000 feet of the blast site about the implosion and has inspected their properties. People don’t have to evacuate, but they must stay inside during the blast, which will be proceeded by warning sirens five minutes, one minute, and 10 seconds before detonation.
Nearby residents say they are uneasy about the project.
“I’m leaving,” said Shontae Davis, who has lived in the house on Center Avenue in East Pittsburgh closest to the bridge for two years. “They have to do what they have to do, I guess. They say it will be safe, but I’m not sure.”
David Gumpher, co-owner of electrical contractor Gumpher Inc. immediately next to the Davis residence but across the line in North Braddock, agreed. He’s concerned about his 20 employees and the property where the business has been located since 2012 after moving from the other end of the bridge.
“They’ve assured me there shouldn’t be any damage to my building,” he said. “I hope they’re right.”
Additionally, Mr. Gumpher wants to be sure the construction doesn’t block access to his driveway adjacent to the bridge. The new bridge will be longer than the existing one by about 25 feet, and that could close off the company’s driveway if too much of the longer structure is on his side of the valley.
“I have concerns, but they say it will be fine,” he said. “I guess we’ll have to wait and see.”
Mr. Shanley said demolition crews had begun placing 96 explosives in 54 spots on the superstructure to drop the steel into the valley. The contractor will take the steel for scrap.
The county said police will restrict traffic around the blast site from 9 a.m. until 10:30 a.m. No traffic will be allowed during that time on O’Connell Boulevard from the 1500 block of Bell Avenue, North Braddock, to the bridge; Center Street in East Pittsburgh from Draper Street to the bridge; Ravine Street in North Braddock from O’Connell to Lewis Street; Poplar Avenue in East Pittsburgh from Draper Street to the end of the road; and Bessemer Avenue from Draper Street to the end.
Once the scrap is removed, crews will start building the new bridge. The entire project will cost $9.95 million.
Mr. Shanley said anyone with questions or concerns about the implosion should call the county at 412-350-2451.
Ed Blazina: eblazina@post-gazette.com, 412-263-1470 or on Twitter @EdBlazina.






Comments
Welcome to Post-Gazette subscriber-only commenting community. Please review our community guidelines.