As they develop plans for highway construction, Pennsylvania Turnpike designers and engineers often order hundreds of core samples and tests so they know the condition of the land they are dealing with.

But expanding an existing road can be far different from building in a new area, as the turnpike is finding out with construction of the Southern Beltway, the 13-mile, $800 million toll road along the Allegheny-Washington county border. The highway, which will connect Interstate 79 with Route 22, is one of the largest completely new toll roads built in decades and in some instances the agency is learning as the project proceeds.

Officials say two aspects of the project, controlling runoff after excavation and plugging old gas and oil wells, have been particularly challenging because crews are building in a long-dormant area.

Near McDonald, where workers excavated 5 million cubic yards of earth for the first section of highway last year, the neighborhood along Route 980 has had a series of flooding issues, including one site where the recently excavated hill collapsed. For wells, the turnpike sought bids based on a maximum of 15 wells only to find 27 as they cleared the construction sites.

Advertise with us

In both instances, the turnpike paid general contractor Joseph B. Fay Co. extra money, $778,685 for the additional wells and $550,000 for additional soil stabilization work. The turnpike commission approved a change order to pay for the extra work this month.

“It’s the unknown,” said Brad Heigel, the turnpike’s chief engineer. “We do a lot of testing to examine what the geology is. Easy to say we should have done something a little differently.

“It’s the biggest risk for the contractor and for us — dealing with the unknown. In the high 90 percents, we get it right.”

Soil: ‘At best difficult’

The path engineers chose for the Southern Beltway passes through what had been a series of mostly grown-over hills and valleys. The first step has been to clear the land, then excavate to reduce the hills and fill in the valleys to create a mostly flat surface for the road bed.

Advertise with us

For the 3.2-mile section near McDonald, Fay spent most of 2017 excavating the area to prepare for construction. Part of that work included a sharp cut of the hill above Route 980 to relocate Reissing Road and prepare for construction of a five-span, 1,370-foot bridge over the existing highway.

From the beginning, there were problems with flooding, something some residents say hadn’t been a problem this serious in more than 45 years. In addition to problems with excavation and runoff controls, the neighborhood has an old, insufficient drainage pipe privately installed by owners decades ago.

It seemed as if when crews addressed one problem, another arose. Whether it rained or not, weeks would go by before a deficiency with another part of the project resulted in residents shoveling mud and pumping water again, recurring circumstances Mr. Heigel called “at best difficult.”

At one point, the hillside where Fay crews excavated to relocate Reissing Road collapsed during a heavy storm that resulted in flooding. The change order, approved after negotiations between the turnpike and contractor and a review by an independent panel, covered the cost of correcting that problem.

In June, turnpike officials met with McDonald area residents and apologized after another round of flooding tied to creation of an access road so workers could erect a bridge beam. It stormed before crews could put runoff controls in place.

Advertise with us

As a result, the turnpike put construction of another retention pond near the new bridge on the fast track. It opened earlier this month and there haven’t been additional flooding problems in weeks.

When the project is finished, Mr. Heigel and his colleagues say, runoff controls should work.

“I would say recently things are improved,” said Steve Hrvoich, the turnpike’s construction engineering manager for the project. “The trap is in place. It’s functioning now.

“[Flooding] is an on-going concern until we’re finished with the project. Any day we don’t get a flood… is a good day.”

Wells: Uncharted area

Advertise with us

For all its forest and brush before this highway project began, the path for the Southern Beltway isn’t virgin territory. In previous decades, coal mines dotted much of the area and McDonald has a long history of oil and gas drilling.

But some of those facilities go back many decades and there is no accurate documentation showing where they are and what condition they are in. That’s particularly true for wells, some of which were drilled in back yards and maintained by individual residents.

In addition, Mr. Heigel said, this is the turnpike’s first project in recent memory that has dealt with old wells at all, let alone so many abandonned, undocumented wells. Turnpike designers searched records and eye-balled the area to develop bid specifications with a set amount of wells only to find a dozen more hidden in the brush when crews cleared the land.

The unexpected wells led to additional payments to the contractor.

“We haven’t had this experience with wells before so it’s all new to us,” Mr. Heigel said. “We were aware of the history of the the area. When we got out there and started clearing the land, we found more than we expected.

Advertise with us

“It’s been an adventure.”

The agency also is learning about the strict rules for dealing with abandoned, uncapped wells, which can begin releasing oil or gas again if they are disturbed and pollute ground water. Many of them are found with branches, stones or other material jammed in them.

“[The Department of Environmental Protection] has pretty strict rules for capping wells,” Mr. Hrvoich said. “We learned pretty quickly that if we touch one, we’re responsible for taking care of it.”

To cap the wells, Fay brought in a specialist as a subcontractor, York Drilling of Mount Morris, Greene County. Mr. Heigel said he expects other contractors will use that company as well.

As far as undocumented wells, the turnpike has hired a company that specializes in drones as it designs future segments of the highway. The company will fly drones with metal detectors over the design area to try to identify as many wells as possible before bid specifications are set.

Advertise with us

Overall, Mr. Heigel said, he’s satisfied designers have done the best they could do on the initial stages of the beltway project. Any changes so far have been comparable to the agency’s average of about 3 percent annually on projects worth about $500 million a year, which he said is below the industry average of about 7 percent.

“Some of this is we’re learning as we go,” Mr. Heigel said.

Ed Blazina: eblazina@post-gazette.com, 412-263-1470 or on Twitter @EdBlazina.