The mission is daunting: Move 27 million cubic yards of soil, each the size of a refrigerator, over a 13-mile area to build the next segment of the Southern Beltway in western Allegheny and northern Washington counties.

It sounds mostly like a labor-intensive project that involves lots of excavators and dump trucks doing lots of digging and loading and dumping.

It’s that, for sure.

But to flatten in 18 months the lumpy terrain that took Mother Nature millions of years to create also takes a mixture of science and art to go along with the muscle: complex calculations and scientific procedures to determine how much dirt to move and where to put it, combined with precise, coordinated movement like the Bolshoi Ballet, with huge dump trucks and excavators in the lead roles, to haul and place all of that material.

Advertise with us

The Post-Gazette will spend the next two years looking at the enormous effort that goes into building the next segment of the Southern Beltway.
Click here to read more.

“There’s actually a science to where the material goes and what we do with it,” Steve Hrvoich, construction engineering manager for the Pennsylvania Turnpike, said in June as he watched crews in the process of razing hills and filling in valleys near bridges that cross Route 22 in Robinson, Washington County.

Here’s what’s involved in moving that much dirt, a key part of the $700 million toll road under construction between Route 22 and Interstate 79:

• Hundreds of test borings to identify what’s under the surface

• Dividing the site into small segments so the material doesn’t have to be carried very far

Advertise with us

• When and where to blast

• How long to let relocated dirt settle before building on it

• Reusing blasted rock to build toe benches to stabilize embankments

A boring start

The process of moving that much soil begins with test borings, hundreds and hundreds of them to find out what is under the surface.

Advertise with us

Before this project started, much of the land was covered in trees, but it was hardly virgin territory. It had been clear cut in previous generations for mining and other activities.

As a result, those borings can find anything from dirt, rock and clay to old mine shafts, pickle liquor sludge (a steel-producing byproduct) and red dog (old shale burned to separate it from coal deposits). Once they know what’s there, engineers plan what to do with it: move the dirt, rock and clay where it’s needed, fill the mine shafts with grout and move the pickle sludge and red dog to inactive parts of the site to bury it for environmental reasons.

Before the work starts, the turnpike commission and contractors submit detailed plans for moving that much soil to the state Department of Environmental Resources for a permit. The agency, in this case through the Washington County Conservation District, is charged with making sure the project has the proper erosion and sedimentation controls in place and monitors the progress.

Those controls usually are the first steps in a highway construction project, Mr. Hrvoich said. For this job, they include a series of retention ponds to catch runoff during and after construction and “miles and miles” of compost filter socks, porous tubes filled with mulch that are placed throughout excavation sites to hold back runoff.

Southern Beltway soil management animation

An artful process

Advertise with us

Actually moving the material is where the art comes in.

Once excavation starts, crews know where they will have to blast rock, setting charges as often as three times a week to loosen the material. If they want to pulverize the rock, charges are set close together; to create bigger pieces to use in stabilization work, the blast pattern is wider.

Engineers divide the excavation site into dozens of smaller segments for a process called balance and fill, precisely gauging how much dirt will have to be moved from a high area to fill in a low area. The key is to use the material within the grid, which costs about $3 a cubic yard, rather than haul it to another part of the project or off site at a cost of about $20 to $40 a cubic yard.

The best example on this job is the daily ballet of the dump trucks and excavators near the Route 22 bridges in Robinson. The bridges, built two years ago, sit waiting while contractors cut down a 90-foot hill about three-quarters of a mile away to fill in a valley and create a relatively level plain on which to build the new road surface.

Here was the scene in mid-August: A hydraulic shovel with an 11-cubic-yard bucket sat on a level site above loose dirt, scooping up material and swinging to the left to drop it in the bed of a dump truck known as a 777D, at 44 cubic yards the largest hauler used in North America. When the truck is filled, it moves away and by the time the shovel swings back with another load, another 777D is there to receive it without delay.

Advertise with us

“You can watch how efficient this is — the next trucks are there to back under the shovel as soon as the other one leaves,” said Bob Kohlmyer, construction supervisor for CDR Maguire, the turnpike’s construction manager for this project.

“There’s no wasted time. That’s where the contractor makes his money.”

At that point, crews had taken down about 65 feet of the hill and had about 25 feet to go.

After the soil has been moved, it is graded and pressed together with a sheepsfoot compactor to reach the right level. In some cases, a site is then put into quarantine for 60 to 90 days for additional settling.

Terry Figola, a construction inspector and lab technician, regularly monitors and measures fields in quarantine. He uses a nuclear density gauge that sends radio waves into the ground and imbedded steel rods surrounded by concrete to measure downward movement, sort of the opposite of a child’s growth chart.

Advertise with us

When the weekly settling is less than 100th of a foot for several weeks in a row, the site is ready for construction.

“Proper compaction is no. 1,” Mr. Figola said.

To create embankments to stabilize hillsides or downward slopes away from road beds, crews use blasted rock to build toe benches at the bottom of sloped areas.

“You have to manage that rock,” Mr. Kohlmyer said last month as he looked out over embankments that already have been put in place in anticipation of road construction. “The turnpike does a good job of making sure that where there’s a need for rock, it’s available on site. We don’t have to bring it in.”

Once the embankments are in place, crews spray them with hydroseed, a sticky mixture made with old newspapers and plant seeds designed to quickly grow vegetation on the slopes to help hold them in place.

Advertise with us

Doesn’t always work

Moving soil can be fraught with complications, some of them outside the control of the best planning and engineering. So it’s not surprising contractors have run into some difficulties moving 27 million cubic yards for this segment of the Southern Beltway project.

Since excavation began in February, the always-fickle climate allowed more-than-expected work during a warmer-than-normal winter, then transitioned into a very rainy late spring and early summer. That creates extra challenges moving soil, causing conditions that Gary Stokum of the Washington County Conservation District called “like trying to push pudding.”

Due to those conditions, contractors clearing about 5 million cubic yards from a hillside above Reissing Road and Route 980 in McDonald to place piers for a new bridge weren’t able to get all of the control measures in place in the order they had planned. That led to minor floods early in construction, then several inches of rain over a few hours on July 12 released a wall of water down the hill, flooding a half dozen homes on Reissing and Route 980, as well as several businesses in McDonald.

Bill Stewart, who slept in his garage for two days because his house along Route 980 was flooded, described living across from the construction site like this: "Maybe this wasn't a flood plain eight weeks ago, but it is now. This is not the peaceful little house in the valley any more."

Advertise with us

Although the Department of Environmental Resources was sympathetic to weather problems, it ordered the turnpike and contractor Joseph B. Fay Co. to complete erosion and sedimentation controls. The turnpike quickly finished that work — and responded to damage claims from homeowners — to regain control of the site.

Then two weeks ago, about 10,000 cubic yards of a finished embankment fell on another part of Reissing Road, about a quarter mile away. Mr. Hrvoich said the turnpike hadn’t accepted that embankment, which was built during a rainy period in July, because inpectors had noticed some instability in it weeks earlier.

It fell before crews could fix it. The soil has been removed and engineers are designing a new embankment.

“It’s not something you expect, but it’s not uncommon, either,” Mr. Hrvoich said. “Especially with that much rain, the site was saturated. On a 5-million-cubic yard job, sometimes you have a slide.”