After delays of about a month, the Freeport Road Bridge over railroad tracks by the Highland Park Bridge will close Monday for 120 days for replacement.

Work on the bridge, which carries about 12,500 vehicles a day between Sharpsburg and Aspinwall, had been expected to begin last month.

“There were weather issues but also utilities took longer than expected to relocate,” said Steve Cowan, spokesman for the Pennsylvania Department of Transportation’s District 11.

As a result, the process of replacing the bridge has been pushed back a month. Instead of reopening in mid-August, the new bridge is expected to open in September.

Advertise with us

Clearwater Construction of Mercer, Pa., has a $4.3 million contract to replace the 85-foot, single-span bridge with precast concrete I-beams.

The project will detour motorists across the Allegheny River to Butler Street via either the 62nd Street or Highland Park bridges.

The closure also will mean changes for Port Authority riders who use the 1 Freeport Road and 91 Butler Street routes.

The 1 Freeport Road route won’t be able to use Main Street in Sharpsburg, where there are a half-dozen stops between Highland Park and 62nd Street. So the contractor will operate a shuttle every 20 minutes from 16th Street in Sharpsburg to a bus stop under the 62nd Street Bridge.

As a result, the 1 Freeport Road bus will follow its normal route through Fox Chapel and Aspinwall to the Highland Park Bridge. Then it will cross the bridge to Butler Street, go back across at 62nd Street and continue to Downtown Pittsburgh on Route 28.

Advertise with us

The 91 Butler Street bus will change its route as well, staying on Route 28 past the Highland Park Bridge to the 62nd Street Bridge, where it will pick up passengers, cross the bridge to Butler Street and proceed to Downtown. That will give Sharpsburg riders two options instead of one during the detour.

The delay in the bridge project also will delay the $2.31 million replacement of a culvert on Freeport Road over Squaw Run near the Waterworks shopping center until the bridge is finished.