Spring won’t officially begin for another two weeks, but that won’t stop the beginning of the annual orange barrel parade as construction crews resume work Monday on some of the region’s biggest road and bridge projects.

And with the work will come a series of new traffic patterns sure to cause early-morning drivers to snap to attention as they reach the areas where changes have been implemented.

One of the most significant changes again this construction season will be on Interstate 376 near Pittsburgh International Airport, where work resumes Monday on a $66.3 million project between the McClaren Road interchange and the Beaver County line.

This year, work shifts from the westbound lanes to the eastbound or inbound side of the highway. Beginning Monday and lasting for more than a month, single-lane, weekday restrictions will be in effect from 7 a.m. to 3 p.m on the outbound side and 9 a.m. to 5 p.m. on the inbound side as Swank Construction prepares for a crossover that will begin in late April or early May.

Advertise with us

Additionally, concrete patching and roadway rehabilitation work will occur on the inbound ramps between Business Loop 376/​Flaugherty Run and Clinton Road adjacent to the highway. Lane and shoulder closures will occur on the ramps through April 5.

During the prep work, the location of the work could shift throughout the corridor from day to day as crews move barriers. Once the crossover starts, the fun begins.

To maintain two lanes of traffic inbound, one of the inbound lanes will be shifted to the outbound side of the road as an express lane for motorists who don’t want to exit in the construction area. The other inbound lane will operate as the local lane, providing the only opportunity to exit at the airport or other interchanges.

That means motorists headed for the airport who are in the wrong lane will have to go the length of the 7.5-mile construction zone, then exit and circle back to get to the airport.

On the outbound side, two lanes of traffic will be maintained by shifting traffic to the right to accommodate the inbound lane. A barrier will be installed between the inbound and outbound traffic, and crews will have two lanes for construction activities on the inbound side.

Advertise with us

Work on the main road should be finished by early September, but work on the ramps won’t be done until November.

On the North Side, outbound traffic will be restricted beginning at 6 Monday morning on Route 65/​Ohio River Boulevard between the Fort Duquesne and McKees Rocks bridges. The single-lane restriction will leave two 11-foot lanes open between the Fort Duquesne and West End bridges and one 11-foot lane open between the West End and McKees Rocks bridges.

Work will include concrete patching, an asphalt overlay, bridge reconstruction, base repairs, drainage and guide rail updates, new signs, retaining wall repairs and pavement-marking installation.

There also will be ramp work as part of this project, but it hasn’t been scheduled yet.

Crews for Lane Construction Corp. worked on the inbound lanes last year as part of the $25.3 million project, which is scheduled to be done by Sept. 7.

Advertise with us

Travel through the North Side should be as restricted as much as last year when inbound work on Route 65 coincided with work on the East Ohio Street/​Route 28 intersection. Most of the East Ohio Street work is done.

The Pennsylvania Department of Transportation plans to adjust the construction schedule to Pirates baseball games and other major city events.

The agency also will begin a multimillion-dollar rehabilitation of Interstate 279 on the North Side this month, but that will involve inbound traffic this year, the opposite of the Route 65 project.

Other projects include the resumption of the $80 million rehabilitation of the Liberty Bridge once Joseph B. Fay Co. finishes long-term repairs as a result of a construction fire in September. Rehabilitation work should resume by April and will include lane restrictions as well as the bridge being closed to all traffic on five weekends and 26 overnights.

Additionally, the Boulevard of the Allies near the bridge will be closed for 80 days this year.

Ed Blazina: eblazina@post-gazette.com or 412-263-1470.