For those who are bummed out about the cold weather, there are a few harbingers of spring on the horizon.
Pirates pitchers and catchers report to Bradenton, Fla., in eight days. Eighteen days after that, daylight saving time returns.
But between those two welcome signs of the season comes this far less desirable one: Construction will resume on the Parkway West, with a long-term closure of the on- and off-ramps at Carnegie scheduled to begin the night of March 2.
The second season of a three-year, $72.8 million reconstruction project promises to be more disruptive than the first, with work extending from Interstate 79 to the Fort Pitt Tunnel over a span of nearly 10 months.
The Pennsylvania Department of Transportation held the first of two public meetings Monday night at the Green Tree Municipal Center to fill drivers in on the details.
The Carnegie ramps will remain closed around-the-clock into December and there will be traffic shifts, narrow lanes, lane closures and full detours galore as the work marches along the parkway from I-79 toward the tunnel.
Read More
“We have a lot going on this year,” said Jim Foringer, PennDOT assistant district executive for construction.
Three separate projects are underway: construction of a fourth outbound lane from Rosslyn Farms through the I-79 interchange; removal of the ceilings in the Fort Pitt Tunnel; and the reconstruction of the parkway mainline, which will cause the biggest and most frequent headaches for drivers this year.
Full overnight closures of the parkway will resume next month in alternating directions between Parkway Center and I-79. PennDOT and its contractor tried maintaining traffic in a single lane overnight when the project began last August but that proved too dangerous.
Six full weekend closures — three in each direction — will be needed during parkway resurfacing, the first coming in late April or early May on the outbound parkway from Rosslyn Farms to I-79.
On four other weekends, traffic will be restricted to a single lane from Friday night to Monday morning to allow work on 15 bridges and three culverts.
Ramps at Banksville Road and Parkway Center will have full weekend closures. The ramp from Poplar Street in Green Tree to the outbound parkway will be closed for a 30-day span, probably in late April or early May, and the Poplar ramp to the inbound parkway will close nightly.
Work on three bridges at the Carnegie interchange will shift all traffic to the inbound side initially, then over to the outbound side as the project progresses, said Denis Mazzoni, project manager for the contractor, Swank Construction Co. of New Kensington. The bridges cross the West Busway, Chartiers Creek and Whiskey Run near the railroad overpass.
West of the bridges, traffic will be shifted toward the shoulders that were rebuilt last summer to allow work on the center median barrier. East of the bridges, work will begin on the shoulders, pinching traffic toward the center.
Lanes will be narrow and boxed in by concrete barriers as they were last year, and the speed limit will be reduced to 45 mph. Mr. Foringer pleaded with those in attendance to tell friends and family to slow down and pay very close attention in the work zone.
“We’ve already talked to the state police about speed enforcement. The problem is there’s no place to pull people over,” he said.
Before the parkway work resumes in earnest, there will be other obstacles for drivers, starting this weekend.
The ceiling removal project will close the inbound Fort Pitt Tunnel from 10 p.m. Friday until 6 a.m. Monday, weather permitting, and again on the weekend of Feb. 20. Traffic will be merged into a single lane and required to exit toward Route 51.
The parkway will be closed in both directions overnight around Rosslyn Farms on Monday and Wednesday next week and possibly on Tuesday for erection of a new sign structure and removal of an old one, Mr. Foringer said.
PennDOT will announce details of the other parkway restrictions and detours as the dates draw nearer.
A project hotline has been set up by the Airport Corridor Transportation Association and it will be staffed weekdays from 8:30 a.m. to 5 p.m. It can be reached at 412-533-4601 or 4602.
A second public meeting on parkway construction will be held at 6 p.m. Thursday at the Carnegie Borough Building, 1 Veterans Way, off West Main Street.