Traveling through the Parkway West construction zone near Carnegie is an exercise in precision driving.

The lanes are 10 1/2 feet wide, 18 inches narrower than usual. Concrete barriers hug both edges of the road through much of the work area.

“There’s not a lot of room for forgiveness,” Pennsylvania Department of Transportation spokesman Steve Cowan said.

Some drivers have learned that the hard way since the work zone was set up in late August. There have been several crashes in or around the zone, including two more on Friday that tied up outbound traffic.

Advertise with us

“There’s not a flaw in the design. The problem is there’s not much room to work in that corridor,” Mr. Cowan said.

The first phase of a $72.8 million project to rehabilitate the parkway from Interstate 79 to the Fort Pitt Tunnels is full-depth reconstruction of the concrete shoulders in both directions from Rosslyn Farms to one-quarter mile east of Carnegie.

The work required placement of a concrete barrier along the edge of the right lanes, which meant that both travel lanes had to be shifted to the left. But there is no space on the left to make up for the space lost to the temporary barrier — that section of the highway has no left shoulder.

That gave PennDOT 21 feet of width to work with — 10 1/2 feet for each lane. A typical sedan is about 6 feet wide; a pickup truck about 6 1/2 feet wide; and a tractor-trailer 8 to 8 1/2 feet wide.

PennDOT imposed a 45 mph speed limit that is displayed on several signs approaching the zone. It placed a solid white line in the center to keep drivers from changing lanes and posted a requirement that trucks and buses stay in the right lane.

Advertise with us

After the project began, it closed the Carnegie on-ramps to both sides of the parkway because ramp traffic could not safely merge.

Then this week, the department announced that it would start closing the parkway overnight rather than continuing a single-lane pattern, again for safety reasons. It said there had been 12 crashes, several close calls and a construction worker struck.

“While we intended to perform this phase of work with single-lane overnight restrictions, the work zone proved too difficult for some drivers to navigate, creating safety concerns for other motorists and our workers,” said Dan Cessna, district executive.

The inbound side will close at I-79 at 10 p.m. on Tuesdays, Thursdays and Saturdays through Oct. 16; the outbound side will close at Green Tree at 10 p.m. Mondays, Wednesdays and Fridays through Oct. 22. The highway will reopen by 6 a.m. weekdays and 10 a.m. on weekends. No Sunday overnight closures are scheduled.

“We’re still assessing what we’ll do for the next phase after the overnight closures,” Mr. Cowan said.

After the shoulders are rebuilt, traffic will be shifted again to allow replacement of the center barrier. Work will expand to other sections of the parkway next year.