Escaping from Downtown via Route 28 has been difficult for a long time. For the next couple weeks, it's going to be even trickier.

At 6 a.m. today, the Pennsylvania Department of Transportation was scheduled to close the northbound Veterans Bridge ramp to Route 28 around-the-clock through May 31 to replace expansion joints and repair the deck -- work that cannot be done with traffic on the ramp.

The posted detour will be to continue to the Parkway North, exiting at Hazlett Street and using East Street and East Ohio Street to reach Route 28. But PennDOT spokesman Jim Struzzi said he expects drivers will find other ways.

The ramp closure is one of three big changes taking effect today through the end of the month as the $17 million second phase of the Veterans Bridge-Crosstown Boulevard rehabilitation project continues.

Advertise with us

The northbound side of the bridge will be restricted to two 11-foot-wide lanes during the day and one lane from 8 p.m. to 10 a.m. daily. "We're going to see how it goes. If it causes too much of a problem we're going to ask the contractor to get off the road earlier," Mr. Struzzi said.

Also closing today is the ramp from Washington Place to the northbound Veterans Bridge. The posted detour looks like a sightseeing tour: right on Bedford Avenue, right on Crawford Avenue past the old Civic Arena site; right on Centre Avenue; cross over I-579; right on Sixth Avenue; right on Grant Street; right on Liberty Avenue; left at 16th Street and cross bridge; left at East Ohio Street; and right at Madison Avenue to reach the Parkway North.

Traffic bound for Route 28 will be directed to turn right at East Ohio to reach the on-ramp.

Mr. Struzzi said police will be deployed at intersections on the various detour routes to help the traffic flow.

The project will bring restrictions and detours throughout this construction season and next as the contractor, Trumbull Corp., works on 16 separate bridge structures that are part of the Veterans Bridge-Crosstown corridor.