Pittsburgh International Airport’s $1.57 billion modernization likely won’t be completed until at least sometime next summer.

That became evident Friday when the Allegheny County Airport Authority board approved an $8.5 million change order that extended the contract of Lighthouse Electric Co. for various construction tasks to the end of June 2025.

Also Friday, Christina Cassotis, authority CEO, detailed another big month of travel at the airport, with August traffic hitting its highest level since 2005.

To date, the authority, which operates Pittsburgh International, has been coy about when the project would be finished, saying only that it would be next year.

Advertise with us

Ms. Cassotis told board members Friday that the opening date would be announced in a few months.

“We’ve got to get that certain,” she said.

The modernization — the centerpiece of which is a new landside building for ticketing, security, and baggage claim — is about 70% complete. “There’s still a lot of work to do,” Ms. Cassotis noted.

In addition to the new terminal, the project involves construction of a five-level garage featuring nearly 4,500 spaces and new roads and bridges.

Asked about the date in the Lighthouse Electric contract extension, authority spokesman Bob Kerlik said, “As we’ve previously said, the project is still on track for a 2025 opening. There will be a substantial completion date for the construction and then several months of testing.

Advertise with us

“We will announce the opening timeline next year. We’re going to make sure we open when people are trained, the building’s tested, and we’re ready to go.”

Information regarding a potential completion date came the same day that authority board members voted to add $32.4 million to the contracts of three firms to resolve outstanding issues and modify contractual milestones related to the modernization.

The changes were negotiated by Ms. Cassotis with three contractors — Daifuku Airport America Corp., Rycon Construction, and W.G. Tomko Inc.

They involve work on four contracts — the baggage handling system; interiors construction; heating, ventilation, and air conditioning; and plumbing and fire suppression related to the development of the new landside building.

Mr. Kerlik said the negotiated modifications did not mean that the project is behind schedule. He said the agreements “set timelines for the substantial completion of these individual contracts, not the project overall.”

Advertise with us

“In managing 61 prime contractors, schedules are adjusted. In some cases, it involves accelerating timelines. In other cases, it pushes others back. That often requires entering into a new agreement with the contractor’s work that’s impacted,” he said.

Mr. Kerlik added that the change orders ratified Friday “are typical for projects of this size. These modifications formalize those individual timelines as we get closer to opening next year, as well as any cost changes,” he said.

Of the $32.4 million, Daifuku will receive $7.8 million for baggage handling work, Rycon $12.8 million for interiors, and Tomko $11.8 million for HVAC and plumbing and fire suppression.

Other changes orders approved Friday relating to the modernization included:

— $2.5 million to PJ Dick/Hunt for construction management, bringing the total contract to $68.4 million;

Advertise with us

— $4.8 million to Solutions4Networks Inc. for network and information technology infrastructure services, increasing the contract to $13.3 million.

— $2.9 million to Rycon, also related to interiors, bringing the total contract to $148.8 million;

— $6.5 million to Wellington Power Corp. for technology, increasing the pact to $76.6 million;

— $325,607 to Urban Tree for various construction tasks, bringing the total contract to $433,607.

In terms of traffic, 935,600 passengers used Pittsburgh International in August — up 12.8% from last year and 48,200 more than in August 2019 before the pandemic.

Advertise with us

Airlines also provided nearly 1.2 million seats in August, up 12.3% from last year and the most since 2006. It represents “a sign of confidence from all sorts of airlines in our market,” Ms. Cassotis said.

Year-to-date traffic, at 6.6 million passengers, is the most since 2007.

August traffic totals are representative of the kind of summer the airport has had. July proved to be its busiest since 2005, with more than 962,000 travelers arriving and departing. In June, the airport reported the highest traffic of any month in 19 years, with 970,800 arriving and departing.

The crowds have caused some issues, particularly in the early morning when it has taken travelers three hours or more to get through the security checkpoint at times.