Pittsburgh International Airport has hit another milestone in its bid to complete a $1.57 billion modernization.

On a sun-drenched Monday morning, workers and Allegheny County Airport Authority officials celebrated the “topping out” of the huge parking garage that is being built a stone’s throw from Pittsburgh International’s new landside terminal.

With the “topping out” — meaning construction crews have hit the highest point in the project — the garage is now just about two-thirds finished, said Paul Hoback, the authority’s executive vice president and chief development officer.

During a short ceremony Monday, Mr. Hoback viewed the “multi-modal complex,” as it is officially described, in symbolic terms.

Advertise with us

“This massive structure that we celebrate today is not just a parking garage. It’s the start of a family vacation. It’s the start of a career-defining business trip. It’s the start of a honeymoon or a reunion,” he said.

The five-level garage will feature nearly 4,500 spaces in all — 3,300 for the public, more than triple the number of covered parking spots currently available at the airport. Another 1,165 spots will be for rental cars.

With additional surface parking surrounding the garage, about 6,100 new spaces will be available for travelers. They will supplement 16,800 existing spaces, all of which will remain.

For travelers in a hurry, the garage will provide a parking guidance system to help locate open spaces. Authority officials are also hoping to obtain an environmentally friendly Parksmart certification, the garage equivalent to a LEED certification for buildings.

So far, nearly half a million trade hours have been poured into the garage project, with another quarter million still to go for the 80 to 100 workers on site, said Brian Peglowski, business manager for Turner Construction.

Advertise with us

The structure that Mr. Hoback saw as a starting point represents an achievement for Mr. Peglowski.

“I think about the next time that I fly with my family down to Florida for vacation and you can look out your window and you can point to that and say, ‘I was part of that,’ ” he said. “We’re leaving a lasting legacy and footprint not only on Allegheny County but the entire region.”

The garage will contain 3,002 pieces of precast concrete. To enliven its appearance, artist Adam Kuby has etched a design into the facade to invoke, as he put it, “a sense of movement, energetic streams, technology grids, connectivity” as well as the “complexity of travel ... circulation and all the crazy ways that every one of us gets from the airport, through the airport and up into the friendly skies.”

“It’s really rare for an artist to be given a canvas this large,” he said.

Wellington Power electricians, from left, Adam Janosko of Jefferson Hills, Dylan Mentzer of Highland Park and Cole Gilbert of Swissvale sign a symbolic last beam at the Pittsburgh International Airport. (Lucy Schaly / Pittsburgh Post-Gazette)

Connected to the garage itself will be a customer services building where travelers can rent cars.

Advertise with us

With the “topping out” done, the garage is about 65% finished, Mr. Hoback said. That’s about the same percentage as the new landside building, which will be used for ticketing, security, and baggage claim.

At the new terminal, virtually all of the facade has been finished, with work now concentrated on building out the interior, Mr. Hoback said. Nearly 40% of the baggage system has been installed.

As the interior construction heats up for summer, the project should be at peak employment, with up to 1,100 people working onsite.

Despite the progress, Mr. Hoback refused to commit to an opening date for the new terminal and garage, saying only that both would be done at the same time in 2025.

The opening date, he said, won’t be announced until it’s about three months away.

Advertise with us

“We think that’s the right thing to do so that we don’t get rushed. As we talked to a lot of other airports that opened, a lot of them said that it is important to make sure you do it right,” he said.

“And we’re going to make sure we do this right. We’re not going to rush it. We’re going to make sure we open when people are trained, the building’s tested, and we’re ready to go.”

The new terminal will be tucked between the C and D concourses of the airport’s existing airside building, where travelers board and get off airplanes. The two terminals will be connected via a bridge and tunnel.

With the changes, the number of gates will be cut from 70 to 58 and number of concessions reduced slightly.

Once the new landside building opens, the existing one, built as part of the midfield terminal construction more than three decades ago, will be either demolished or repurposed. The tram that runs between landside and airside will be shut down for good.

Mark Belko: mbelko@post-gazette.com