As the work hits the halfway point, the cost of the Pittsburgh International Airport modernization has climbed by $170 million to $1.57 billion.

Allegheny County Airport Authority officials attributed the increase Tuesday to escalating costs in procuring structural steel; concrete and rebar; components like flight information display boards, digital screens, servers and fiber optic cables; and flooring, paint, walls and other finishes.

In its Blue Sky News blog, the authority, which operates Pittsburgh International, stated that the airlines that fly from the Findlay airport had unanimously approved the 12% increase in the cost.

Those carriers will be responsible for paying for the bulk of the improvements, which include a new landside terminal for ticketing and security, through increases in their rates and charges.

Advertise with us

Four months ago, airport officials had said that the modernization project was still within the $1.4 billion budget, in part because the authority bid some of the work early to avoid long lead times.

But in announcing the increase Tuesday, the authority stated that circumstances had changed because of “pandemic-related inflation and supply chain shortages.”

Nonetheless, it maintained that the cost increase is still below that of other building projects in the Pittsburgh region. It cited the Engineering News-Record construction cost index, which estimated that local building costs have jumped about 30% since 2019.

According to the Associated General Contractors of America, nonresidential construction costs soared 38% between February 2020 and April 2023. The good news is that they dropped 1.1% between April 2022 and April 2023.

Cement and gypsum building material costs also have seen increases over the past year, 13.7% and 12.1% respectively through April, the association found.

Advertise with us

The airport modernization will feature a new landside building for ticketing, security and baggage claim; new roads to and from it; and a five-level parking garage with 4,200 spaces. The new facility will connect to the existing airside building, where travelers board and get off planes.

Once the project is finished, the authority plans to either demolish or repurpose the current landside building and discontinue the use of the tram that has whisked travelers between it and airside since the midfield terminal opened in 1992. The authority plans to continue operating the short-term parking garage next to the landside building.

Completion of the modernization is scheduled for the first quarter of 2025 after the end of the busy Thanksgiving and Christmas travel season.

In the past, airport CEO Christina Cassotis has said that the new terminal is needed in part to right size the airport after the loss of the US Airways hub in 2004, which resulted in a significant plunge in flights and traffic.

Authority officials have said no local or state tax dollars would be used to help pay for the construction. However, it has received $23.5 million in federal grants to offset the cost.

Advertise with us

In addition, the authority has targeted a $6 customer facility charge paid by people who rent vehicles at the terminal, state gambling revenues, and money generated by natural gas drilling on airport property to help cover the cost.

It also got permission from the Federal Aviation Administration to dedicate much of the $4.50 passenger facility charge paid by each traveler who gets on a plane to help pay for the project. It has estimated that it will use $345 million in PFC revenues for that purpose, with $275 million earmarked to help pay off the debt.

The authority floated an $832.7 million bond issue in 2021 to finance part of the construction. It is considering a second bond issue to help pay for the rest. It plans to pay back the bonds through the revenue generated from the airlines and the other sources.

Representatives for Southwest Airlines and American Airlines, Pittsburgh International’s two largest carriers, did not return emails seeking comment on the increase in the cost of the modernization.

The cost to the airlines to board a passenger at Pittsburgh International increased 15.9% to $11.97 in January. It was the second time in three years the cost has risen, although it still was lower than the high of $14.97 in 2011.

Advertise with us

Authority officials attributed the jump to inflation and to rising costs as travel and operations pick up to near pre-pandemic levels. They said it had nothing to do with the modernization since those debt payments don’t start until 2025.

Mark Belko: mbelko@post-gazette.com