The Columbus, Ohio, firm tasked with developing the land between PNC Park and Acrisure Stadium on the North Shore will get more time to craft a game plan for the last of the parcels still to be transformed.
Pittsburgh Stadium Authority board members have given Continental Real Estate Companies three more years until Dec. 31, 2027, to develop Gold Lot 2, the parking lot located directly behind the mixed-use building that houses Burgatory, Tequila Cowboy, and Pittsburgh Post-Gazette offices.
Without last month’s action, Continental would have been on the hook to start developing the land by Dec. 31, 2024.
The extension comes as the Pittsburgh Pirates take the first steps next week toward creating a 30,000-square-foot outdoor plaza at the corner of Mazeroski Way and West General Robinson Street next to PNC Park.
They will brief the city planning commission Tuesday on their plans to install a 40 ½ -foot wide by nearly 23-foot high LED screen at the site, which is part of the option area Continental typically would be responsible for developing.
In this case, the Pirates are buying the parcel outright and working with HiLife Hospitality to program the space, which will also include two stages and a covered beer garden next to a food stand. In addition, the baseball team is buying a 15,000-square-foot space located on the ground floor of the six-story apartment building Continental is building at the intersection of Mazeroski Way and North Shore Drive.
Read More
The Pirates and HiLife are planning a restaurant, bar, and experiential entertainment venue in that space to complement the offerings in the adjacent plaza.
In granting the three-year extension to develop the Stadium Authority-owned Lot 2, board members wanted to give Continental time to determine what would be the “highest and best use” for the parcel taking into account all that has been developed on the North Shore, chairman Stanley Lederman said Friday.
“It may stay parking. Who knows? We wanted to give them time so we weren’t making a decision without appropriate background material,” he said.
Mr. Lederman was not aware of any plans Continental had for developing the space, which is across the street from Stage AE and a long block from the proposed plaza. He noted the point of the extension was to give the developer time to “flesh out” ideas.
“We don’t want to jump the gun and say we’re going to do A, B, or C,” he said.
Mike Hudec, Continental’s director of development in Pittsburgh, could not be reached for comment.
Lot 2 has been a source of controversy in the past.

In 2019, then Mayor Bill Peduto criticized the Steelers for dragging their feet in developing the parcel since the team got part of the parking revenue from the lot on football game days as did the Pirates when they played at home. At the time, Mr. Peduto was pushing to have the lot redeveloped into housing. He vowed then that Continental only would get an extension to develop the property if there were a firm deadline attached to it. If there was no activity by the deadline, the land would revert to the stadium authority.
Two months later, the city and Continental reached a deal that led to the development of the apartment complex at Mazeroski Way and North Shore Drive as well as a parking garage adjacent to it.
Furthermore, the agreement gave the company until Dec. 31, 2024, to start developing Lot 2. The deadline at the time was May, 2021.
It also provided the stadium authority the option of seeking other developers to work the plot if Continental missed the deadline, but the board obviously decided against that in granting the latest extension.
Mr. Lederman said the amendment was “pretty normal and reasonable” given that the Pirates are not expected to have the plaza opened until March 2025. He added that he expects the apartment building to be done before that, though he didn’t have an exact date.
The Pirates are hoping to use the plaza, which will be located directly across from PNC Park’s home plate entrance, not only for activities related to game days but to draw crowds to the North Shore other times during the year by offering movies, entertainment, concerts, fitness classes, and other events.

The LED screen, which will flank the west side of the plaza next to the Champions parking garage, will feature Pirates-centric content on game days. At other times it will be used for movies, videos, or watch parties.
Once the apartment and plaza projects are finished, Lot 2 will become the final parcel Continental, in conjunction with the Steelers and the Pirates, must develop to close out the option agreement reached with the stadium authority two decades ago.
Since then, Continental has produced four office buildings, Stage AE, a hotel, and more than 100,000 square feet of retail space on the North Shore between the two sports venues.