The Pittsburgh Parking Authority is ready to move ahead with a plan to demolish and replace a deteriorating 586-space parking garage at Ninth Street and Penn Avenue Downtown.

Authority officials are expected to brief the city planning commission Tuesday on the first stage of the project — the razing of the six-story structure at a cost of about $2 million.

Based on the application submitted to the commission, the authority hopes to start the demolition in May, with the work expected to take four to six months to complete.

The authority plans to follow the demolition with construction of a 663-space garage with another 70 spaces for bicycles. That work could start in September, with completion of the nine-story structure targeted for November 2020, according to a timetable provided to the commission.

Advertise with us

Authority officials are moving ahead with the construction after a proposal to build up to 185 high-end condominiums and 30,000 square feet of retail along with a 935-space garage collapsed last year.

In its application, the authority stated there would be “provisions for future overbuild of residential or commercial” included in the garage construction, which it described as a “building block for future development.”

Authority executive director David Onorato could not be reached for comment.

In a recent interview, Pittsburgh Mayor Bill Peduto said the old garage, opened in 1958, would be demolished and replaced while talks continued over a broader project at the site.

Boston-based The Davis Companies, which was working with the parking authority and the Pittsburgh Cultural Trust on the condo and retail development, no longer is involved.

Advertise with us

The deal fell through over a disagreement on phasing. The Davis Companies wanted to do a $40 million first phase that would have included about 30 condos and street-level retail.

But the Pittsburgh Cultural Trust, which owns several of the parcels needed for the development, wanted the firm to build another 80-unit condo tower at the same time — a risk The Davis Companies felt uncomfortable in taking.

Mark Belko: mbelko@post-gazette.com or 412-263-1262.