Reader John Kutz asked The Neighborhood team for help in finding the answer to this question: “What is the status of the parking garage at 9th and Penn? Last Tuesday evening it was closed. Is it closed permanently?”

Business reporter Mark Belko has the answer below.

The Pittsburgh Parking Authority has closed a 586-space garage at Ninth Street and Penn Avenue Downtown in preparation for its razing.

Demolition is expected to start in two to four weeks to clear the site for the construction of a replacement garage of about 700 spaces with another 70 slots for bicycles, said David Onorato, the authority’s executive director.

Advertise with us

The authority is moving ahead with the razing after a proposal to build up to 185 high-end condominiums and 30,000 square feet of retail in conjunction with a 935-space garage fizzled last May.

Based on an application filed with the city’s planning commission, the demolition is expected to cost about $2 million. Mr. Onorato said the work will take about five months.

The parking authority hopes to complete the new garage by the summer or fall of 2020. Construction is expected to start early next year.

In a release issued last month, Mr. Onorato said the new garage would be a “green, ‘ParkSmart’ structure in every respect, offering parking customers the latest generation of amenities available in our industry while also meeting the streetscape standards of its central Cultural District location.”

Among the amenities included on the site will be electric vehicle chargers, bike racks and stations, and a water management system.

Advertise with us

Enter The Neighborhood for more like this

In its planning commission application, the authority stated that there would be “provisions for future overbuild of residential or commercial” included in the garage construction.

Pittsburgh Mayor Bill Peduto said earlier this year that the just-closed garage, which opened in 1958, would be demolished while talks continued over a broader project at the site.

Proposals for the condo and retail development collapsed as a result of a disagreement between Boston-based The Davis Companies and the Pittsburgh Cultural Trust over its phasing.

Officials with The Davis Companies wanted to do a $40 million first phase that would have included about 30 condos and street-level retail.

Advertise with us

But the Pittsburgh Cultural Trust, which owns several of the parcels needed for the development, wanted the firm to build another 80-unit condo tower at the same time. The Davis Companies did not feel comfortable taking that risk.

Mr. Onorato said the authority is working with the Cultural Trust to give it more frontage on Penn Avenue for a future development, while moving the garage footprint back toward the middle of the block.

Mark Belko: mbelko@post-gazette.com or 412-263-1262.