The developers behind a plan to convert the historic Alfred E. Hunt Armory in Shadyside into an ice skating complex are scrambling to find more money for the project because of an increase in construction costs.

Mosites Co. and partners B. Lafe Metz and David Light are in discussions with the city’s Urban Redevelopment Authority about extending the six-month period of exclusive negotiations for the possible sale of the 93,671-square-foot building while they try to find more capital for the venture.

The developers are facing about a $5 million increase in the $32 million construction budget as a result of inspections by structural and geo-technical engineers and specialty ice consultants who have visited the East End landmark, Mr. Metz said.

He described the reason for the increase as “basically engineering concerns.” The developers are working with the city and URA to “determine if we can collectively pull all of the money together” needed to close the gap, he said.

Advertise with us

“There’s a desire on the part of the developer and the city and some of the universities that would be playing there for the project to happen. We’re collectively exhausting every possible option for pulling the funding together. We’re cautiously optimistic,” Mr. Metz said.

He added he and his partners also are working with their architect and engineers to see if there is a way they can trim the overall cost of the construction.

The URA board authorized six months of exclusive negotiations with Mosites and its partners in December for a possible sale of the armory for a minimum price of $1.8 million.

That exclusive period expired in mid-June.

“They acknowledge that we have been working hard on all of the due diligence and that we have been spending a lot of money bringing the project together,” Mr. Metz said. “It’s been a good partnership, and they have been very cooperative.”

Advertise with us

An extension is warranted, given how close the parties are “toward finalizing the financial commitments,” said URA board chairman Kevin Acklin, former chief of staff to Mayor Bill Peduto.

“The URA is continuing to work alongside the city and the Mosites development team to minimize the project costs and close any remaining gap, so that we can deliver on this opportunity to build an urban ice rink facility and public parking asset,” Mr. Acklin said.

“We have made tremendous progress in proving the viability of the development while preserving Hunt Armory as a historic building. We believe this project is worthy of investment, as it will support public recreation options and provide additional parking for small businesses in the growing eastern neighborhoods of the city.”

The proposal by the Mosites development team includes a full-size hockey rink and a smaller “studio” rink. There also are plans for 24,000 square feet of office space, 100 to 115 parking spaces, and retail and classrooms.

Mr. Acklin said the URA or an affiliate likely would own a share of the office component, with revenue used to support the recreational facilities.

Advertise with us

As currently envisioned, the Pittsburgh Parking Authority would own and operate the parking component. A new parking tax increment would be used to help construct the building’s ice arena, which also would be publicly owned, Mr. Acklin said.

“The ownership structure is still being negotiated, but since public money is proposed to be invested, the public should own a substantial portion of the project,” he said.

Mr. Metz said the development team already has agreements in principal with potential ice rink users. One is Chatham University, which has talked to the group about using the armory for its men’s and women’s hockey teams.

The Mosites team also has been working on agreements with two other possible hockey tenants, one believed to be an amateur hockey association and the other a high school. It has been talking to the Pittsburgh Penguins about a possible agreement to operate and manage the Armory rinks.

Steve Mosites, the Mosites Co. president, said he would like to start construction in late spring 2019 and have the ice facilities available to tenants and the public by September 2020.

Advertise with us

As part of the potential funding, Mosites and its partners are seeking a $5 million state redevelopment assistance capital grant and more than $5 million in historic tax credits.

While there’s still much work to be done, Mr. Mosites feels good about where the project stands.

“I think there’s enough momentum that there’s a good chance this could happen,” he said.