The owners of the abandoned Century III Mall in West Mifflin have been given about a month to show that they are working toward demolishing the building before the court determines whether the state will take over the property.
On Friday, Allegheny County Common Pleas Court Judge Jill Rangos gave Century III Mall PA LLC approximately 30 days to provide evidence that they are moving forward in good faith on their promise to raze the 1.1-million-square-foot building.
The mall’s attorney Steven Townsend said a contract has already been signed to begin the demolition process, which he called “probably the biggest [demolition contract] in Western Pennsylvania,” although he did not disclose the amount.
Mr. Townsend also said the company hired a private contractor to conduct an asbestos inspection and heavy demolition equipment is currently at the site.
The company has made slow progress towards demolition of the building, which has fallen into ruin, causing concern due to its attractiveness to urban explorers despite it being a safety hazard.
Last April, a fire burned through the building, summoning hundreds of firefighters from across Western Pennsylvania and a teenage trespasser was seriously injured months later after falling through the roof.
Read More
“We’re abating the nuisance now but it doesn’t happen overnight,” Mr. Townsend said.
Prosecutors from Allegheny County District Attorney Stephen Zappala’s office in January filed criminal charges of causing or risking a catastrophe and making a public nuisance against the owners. He also filed a petition seeking to take possession of the property that would allow his office to solicit bids to have it demolished.
The mall’s owners asked for a 30-day postponement on the matter.
Deputy District Attorney Jon Pittman called the request for postponement a “last ditch effort ... to fight the government at any turn.”
However, when asked how long it would take to demolish the building if the government takes over the property, Mr. Pittman said he did not have a timeline, although the first step would be to request funds for the project from the General Assembly — a cost estimated to be between $15 and $20 million.
Ultimately, Judge Rangos granted the continuation and urged the owners, prosecutors, and officials in West Mifflin to work together.
She also ordered the owners to bring proof of their progress to the next hearing, including documentation of the wire transfer deposit sent to the demolition contractor, the asbestos inspection, and photographs of heavy equipment at the site.
“West Mifflin needs to be assured because they feel like they have been burned in the past,” Judge Rangos said.
West Mifflin Solicitor Phil DiLucente said he and county prosecutors were hoping the temporary restraining order would have been put in place as planned on Friday, but he understood Judge Rangos’ decision.
“We’re frustrated, but we believe it was a prudent decision and at least the taxpayers are seeing movement.” Mr. DiLucente said. “This council and this mayor have stressed that this is priority number one for over two years now so hopefully the conditions [of the judge’s order] are met.”
Correction, posted May 28, 2025: In an earlier version of this story, the owner of Century III Mall was identified incorrectly. Quotes from the earlier version of the story have also been updated to conform to the hearing transcript, which was not available until after the story was originally published. In the earlier version, Judge Rangos’ name was misspelled, and the story has been updated with the correct spelling throughout.






Comments
Welcome to Post-Gazette subscriber-only commenting community. Please review our community guidelines.