A first step to building a smarter natural gas pipeline system in Pennsylvania is to build a better map.

Again and again in the first draft of a report of recommended practices that was released last week by a pipeline task force convened by Gov. Tom Wolf, stakeholders said comprehensive maps of the state’s present and planned pipelines — and all of the valuable features they might intersect — would make it easier to decide where best to put them all.

That theme was one among several that emerged from the 184 recommendations made by 12 work groups tasked with making the anticipated build-out of tens of thousands of new miles of pipelines tied to Marcellus and Utica shale wells in Pennsylvania over the next two decades the least intrusive possible.

Shared maps could help communities fit pipelines into their comprehensive plans; infrastructure developers avoid sensitive locations; businesses take advantage of local fuel; and emergency responders prepare in case the lines fail, the report’s authors wrote.

Advertise with us

Other common threads in the 335-page draft report, by groups with interests in everything from agriculture to archaeology and environmental protection to economic development, included suggestions for smarter and earlier planning that is more open to the public and an emphasis on taking a broader view across multiple projects, community borders, regulatory jurisdictions and time.

Right now, the draft report says, “Permits are not reviewed for the cumulative and long-term impacts at a landscape level. Chosen routes do not necessarily avoid sensitive lands, habitats and natural features, nor are the impacts to natural and cultural resources, landowners and communities along them always minimized or mitigated.”

Such a lack of smart planning, the report says, can waste financial resources and “lead to individual decisions accumulating into a much broader and longer impact” on citizens and lands than is necessary.

The task force’s draft suggestions to improve Pennsylvania’s pipeline development range from the very specific — “Use Dry Seals for Centrifugal Compressors” — to the lofty — “Enhance STEM (Science, Technology, Engineering and Math) Education.”

Some suggestions, like reseeding right-of-ways with native plants, would require a change in behavior. Others, like giving the state Public Utility Commission new authority to enforce safety standards for gathering lines in low-population areas, could require a change of law.

Advertise with us

The final report, which is due to the governor in February, will also require the authors to reach a consensus on issues that are still being debated. The Local Government work group, for example, recommended that pipeline companies provide maps of finished lines to local governments but noted “most of industry generally disagrees with this concept” out of concern that people would use the maps instead of the PA One Call service to check for pipelines before digging.

The task force is holding a meeting to discuss the draft in Harrisburg on Nov. 18. It will also take outside feedback into consideration. A public comment period on the draft is expected to open at the end of the week and last for 30 days.

Laura Legere: llegere@post-gazette.com.