Building the first nuclear power plants in 30 years in the United States came with all sorts of challenges, as Anya Litvak’s two-part package on the Westinghouse Electric Co. bankruptcy makes clear.

For one thing, the U.S. has lost a lot of manufacturing capacity in that time. So when the Cranberry nuclear firm signed up to help build new plants in Georgia and South Carolina, some massive parts needed for the projects had to be made in other countries and transported here.

Steam generators for the AP1000 plants weighed more than 1.3 million pounds each and spanned more than 80 feet.

Westinghouse had to modify the nation’s largest train car and cut down trees along the route to transport them from a port in Savannah to the site.

Advertise with us

A risk manager assessing the challenges decided to use NASA projects as a reference, since the nuclear plants were so complex and so massive. Plus they had to deal with lots of regulation.

The regulatory issues, according to the Pittsburgh Post-Gazette story, had an impact on productivity.

The AP1000 design was meant to take advantage of modular construction, making it easier to bring in big pieces and then quickly assemble the plant on site.

Except that when parts coming out of a factory in Louisiana arrived at sites, quality control inspectors went over them to document deficiencies. Workers took them apart to fix problems — negating the promise of modular construction.

In addition, some workers weren’t familiar with the security conscious nuclear construction culture. If they lost documentation for parts, “mountains of metal were put out to pasture in large laydown yards,” according to the story. “A ding in the chain of custody of a nuclear component renders it useless.”

Advertise with us

Productivity on both sites reached a low in early 2016.

Each 10 percent decrease in productivity, a consulting firm estimated, added $203 million to the rapidly skyrocketing price tag.