The Pennsylvania Department of Environmental Protection has fined two natural gas infrastructure companies for incidents related to operations in the Marcellus Shale play.

Houston-based midstream company MarkWest Energy Partners faces two fines totaling about $151,000 for flaring violations at its processing plant in Washington County, the DEP said.

The DEP also fined NFG Midstream Trout Run LLC of Erie $250,000 for multiple violations during construction of the Trout Run Gathering System pipeline in Lycoming County.

According to a consent order issued in April, the department fined MarkWest more than $71,000 due to improper flaring. Neighbors of the company’s Houston Gas Processing Plant in Chartiers Township reported on several occasions seeing black smoke coming from the plant. The DEP fined the company for not following flaring protocols and for air pollution.

Advertise with us

Meanwhile, a second consent order dated Aug. 4 issued an $80,000 fine to MarkWest for conducting flaring operations without a permit at the same facility. The order states that MarkWest said the violation was due to “the company’s inadvertent failure to seek department authorization of the fractionator flare as an emissions point in the plan approval for the Houston plant.”

A company spokesman elaborated on that Wednesday. "In 2011, MarkWest installed a new process control device intended to enhance the operational safety of the plant and the surrounding community,“ Robert McHale, MarkWest spokesman, said in an emailed statement. ”In implementing this improvement, MarkWest inadvertently omitted the newly configured flare from the permitting process. The recent consent order is intended to address that oversight."

As a condition of the consent order, MarkWest is expected to seek a permit application.

The DEP announced Wednesday it also had fined NFG Midstream Trout Run LLC, a subsidiary of New York-based National Fuel Gas, $250,000 for multiple violations of the Clean Streams Law and department regulations during construction of the Trout Run Gathering System pipeline in five Lycoming County municipalities during 2011 and 2012.

“Department staff documented continuing violations at multiple locations during a seven-month period,” John Ryder, DEP’s director of district oil and gas operations, said in a statement issued Wednesday. “NFG’s failure to implement and maintain erosion and sediment control best management practices resulted in several sediment discharges into unnamed tributaries to Mill Creek and Lycoming Creek, Lycoming Creek, and an exceptional value wetland.”

Advertise with us

The department’s investigation began in October 2011 when inspectors “discovered sediment on State Route 973, no temporary stabilization, and ineffective best management practices used to control erosion and sedimentation issues,” according to the DEP.

Periodic inspections by department staff during construction of the 16-mile gathering line resulted in the issuance of 13 violation notices to NFG, including 12 violations for sediment discharges to waterways, the DEP said.

While the sediment discharges did impact the waterways, the department did not document any impact to fish or other aquatic life from any of the violations. NFG has instituted additional environmental protocols since this time and has addressed the environmental issues identified on this project, DEP said.

The pipeline begins at a Seneca Resources well pad in McIntyre Township and ends at an interconnect station at the Transco transmission pipeline in Loyalsock Township.

NFG paid the penalty on Sept. 18, DEP said.

Stephanie Ritenbaugh: sritenbaugh@post-gazette.com or 412-263-4910