Nearly three weeks after a massive storm ripped through southwestern Pennsylvania, killing three, knocking out power to more than 400,000 and leaving behind destroyed homes and businesses, Verizon says it has restored internet, cell phone and WiFi services to all customers.
That announcement Saturday came after Churchill residents complained on Friday that they still were awaiting a total return to normalcy.
Duquesne Light was able to restore electric power to all residents within 10 days of the April 29 storm, but some Verizon customers were still waiting late last week to be reconnected to wireless services.
Verizon spokesman Jeff Kew said Saturday that the company had been able to restore all services for all customers.
Mr. Kew had said on Friday that the company needed to wait for clearance from electricity providers before it could respond to its outages. Duquesne Light officials said the extensive damage, especially in Churchill, “required a prolonged response” and the company had to follow normal processes to eliminate safety hazards and replace broken poles before allowing other utilities to move in.
A Duquesne Light official said via e-mail Saturday that the utility was “not aware of any ongoing issues on our end that would prevent Verizon from completing their work.” And later in the day, Mr. Kew confirmed that service was back for all.
Read More
Christian Markiewicz, 23, of Churchill considers himself lucky because he got his phone service restored Wednesday. But living without cell or internet service for two weeks was tough, he said, leaving him to rely on his family’s monthly data allowance and hotspot — until both ran out.
“I couldn’t even call on my cell phone for that first week; I would have to go down to Monroeville to get reception,” he said. “At first it didn’t seem like a horrible thing, because we could just go outside and find stuff to do, but once it gets dark out, it definitely becomes frustrating and hard to deal with.”
Officials have said the storm damage was unlike anything they’d seen. Wind gusts in some areas reached 95 mph – the equivalent of a Category 1 hurricane — toppling trees, shearing utility poles and snapping power lines across the region. Three people died in storm-related incidents.
City and county officials declared a disaster emergency, allowing them to bypass normal bidding procedures and immediately deploy all available resources for emergency response and recovery. County Executive Sara Innamorato has extended the county declaration until June 6.
The extended time without electricity, internet or cell service was taxing, said Carol Wood, 75. She and her husband, Mike, were lucky if they could get one bar of cell service, and spotty connections left them cut off from updates regarding restoration and recovery from local officials and utility providers, they said.
For days, the couple did what they could to help clear storm debris obstructing the roads as they waited, not knowing when — or whether — someone would come with help or answers.
“We were blocked in from both sides of the street and kind of stuck here,” Ms. Wood said. “There was a tree trunk in the middle of the street and we had to cut the top of the tree ourselves just to get out.”
Blackridge, where the Woods live, is in parts of three municipalities: Penn Hills, Churchill and Wilkinsburg.
Residents said they grew increasingly frustrated as they watched other neighbors get power and cell service restored within two days of the storm while their households remained in the dark and off the grid for nearly two weeks.
Churchill Mayor Paul Gamrat said the municipality received multiple reports from residents regarding electric, phone and internet outages who said they had no communication regarding restoration times.
“On one street there’s Wilkinsburg and on the other there’s Penn Hills, and all of their roads are open and you would see them walking around,” said Mr. Wood, 72. “It was as soon as you hit Churchill that it was a mess.”
About 400,000 people in the region were without power at some point within the first week of what Duquesne Light officials called an “unprecedented storm.”
With the help of 600 additional electrical workers and assistance from city departments, Duquesne Light replaced 300 poles, restrung about 250,000 feet of wire and replaced nearly 250 transformers within a week of the storm, spokesman Matt Neistein said.
By May 6, about 98% of Duquesne Light’s customers had power back, and full restoration for all remaining customers was completed by May 9, the utility said. Mr. Neistein said the region’s challenging topography layered with continuing bands of rainy weather made recovery efforts more difficult.
Duquesne Light officials couldn’t say whether Churchill was one of the last communities to have service restored, but acknowledged the borough “experienced considerable damage.”