The Pennsylvania Turnpike will build a new interchange at Route 981 in Mount Pleasant, Westmoreland County, in the next couple of years before it builds one at Route 130 in Penn Township.

The turnpike commission on Tuesday approved adding the Route 981 interchange to its capital projects budget. The plan is to use an innovative design-build process as the first pilot under a program approved earlier this year by the state Legislature.

CEO Mark Compton said in an interview before the meeting that the turnpike decided to “pause” the interchange at Route 130 because preliminary engineering studies showed more improvements have to be made to local roadways to handle additional traffic from the interchange.

Instead, the agency will move ahead with the Route 981 interchange, which Compton called “a little bit lower hanging fruit” because that highway already has excess capacity and is going through additional improvements.

Advertise with us

Pilot project

The interchange will be among the first new interchanges built without a toll plaza since the turnpike went to open-road tolling, where vehicles drive under a toll gantry that either charges a motorist’s E-ZPass transponder or takes a license plate photo and sends a bill for the toll. That system, which begins in Western Pennsylvania at the beginning of 2027, will allow free-flowing ramps on and off the turnpike like other interstate highways because there will be no need for toll booths.

“We wanted to make sure we did something for Westmoreland County,” Compton said. “We can, in fairly short order, move ahead with this project. This has been a regional desire as well.”

The turnpike pushed for the design-build option, which allows work to start long before a project has been fully designed, for its projected $1.6 billion joint project with New Jersey to upgrade the Delaware River Bridge. That project on Interstate 95 is still under design, so the turnpike will use the estimated $45 million Route 981 project as a test run of the new option.

Pittsburgh and the state Department of Transportation used that method on an emergency basis to replace the Fern Hollow Bridge after it collapsed into Frick Park in January 2022.

“We are viewing this as a fast-track project,” Compton said, adding that the agency will design about 20% of the project before putting it out for proposals to design and build the rest at the same time. The preliminary design either will go out for bid or be added to an existing design contract the turnpike already has.

Advertise with us

Local officials say they understand the reasoning and support the idea of the Route 981 interchange moving ahead first.

“We have an opportunity here to move one of these ahead, and it’s going to be Route 981,” state Sen. Kim Ward, R-Hempfield and Senate president pro tempore. “The road work is done. The acquisition is done. It’s ready.”

Ward said Westmoreland County commissioners, who couldn’t be reached for comment, also support the decision.

State Rep. Brian Rasel, R-Irwin, whose district includes Penn Township, agreed. The township has been pushing for the interchange between Irwin and Monroeville for about 20 years and expected to have it under construction by now after it was approved for design in 2024 before turnpike financial difficulties pushed construction back to about 2035.

“I understand it,” Rasel said. “One is shovel ready and one is not. That sounds reasonable to me.”

Advertise with us

Airport help

In a statement, the state Department of Transportation noted Route 981 is in the second phase of three phases of improvement work known as the Laurel Valley Transportation Improvement Project that could cost about $230 million.

The first 4.5 miles, from interchange Route 819 in Mount Pleasant Borough to the Norvelt area of Mount Pleasant Township, was completed in 2024. The second phase currently under construction until 2029 makes improvements to 2.5 miles along Hill Churches Road/Bell Memorial Church Road from Bingham Road in Mount Pleasant Township toward Route 981 at Airport Road in Unity.

Section 3, 3.5 miles of Route 981 from Norvelt to Bingham Road just south of Route 130 in Unity, is in preliminary discussion and scheduled to begin three years of construction in 2029.

“When you look at the three projects together, you can see the larger vision: a modernized Route 981 corridor,” PennDOT District 12 Executive Rachel Duda said in a statement. “This positions the region to take advantage of the additional connectivity the turnpike interchange will provide.

“It’s a significant investment in the future of this region. Not only improving travel for the people who use Route 981 today but preparing the corridor for future economic development, increased access and new opportunities.”

Advertise with us

The new interchange would be in the Carpentertown area, about 6 miles east of the New Stanton interchange and 10 miles west of the Donegal interchange.

The project is expected to be a boost for Arnold Palmer Regional Airport, which will be about 10 miles from the new interchange. The airport was left without a major airline when Spirit closed earlier this year.

“It would be a big benefit for the airport,” said Moe Haas, executive director of the Westmoreland County Airport Authority. “It would make for an easy trip from the turnpike for passengers who don’t want to go to Pittsburgh International.”

Haas said the authority is expecting a decision by October on a federal grant from the Small Community Airport Development program. The agency could use the $850,000 grant as an incentive to attract a new lead airline, Haas said, and knowing the turnpike interchange would be coming could encourage that commitment.

Dan DeBone, president and CEO of the Westmoreland County Chamber of Commerce, said the agency supports both interchange projects. But he said the airport corridor is especially important for the region.

Advertise with us

“From an economic development standpoint, the Route 981 project makes sense for Westmoreland County,” he said. “At the same time, when the other project is ready, it needs to move forward, too.”

Route 130 work continues

Ward and Compton stressed that work will continue on the Route 130 interchange.

“The Route 130 project will continue to go forward,” Ward said. “I say be patient. We will continue to push this forward.”

Compton said it would not have been “prudent” for the turnpike to move to construction at Route 130 knowing local roads would have been overrun with additional traffic. The cost of the Route 130 interchange likely will increase from the $40 million to $60 million projection because of the need for more local road improvements to do the project correctly.

“Project delays aren’t uncommon,” he said. “Those off-site improvements are going to take more money than we expected.

Advertise with us

“But the project isn’t dead. It’s not going away.”

Work is continuing to finish designing a turnpike-widening project being done in two sections between Irwin and Monroeville. The Route 130 interchange remains on schedule for about 2035, after the first section of widening is completed.