Mammoet, the Netherlands-based company considered a worldwide specialist in moving heavy things, has a history of making history.
Or, in its own words: “Making the impossible possible.”
Over the years, the company has played key roles in projects such as placing a protective cap on top of the Chernobyl nuclear power plant, raising a sunken Russian nuclear sub from the floor of the Barents Sea, and floating sections of the 2.5-mile North Portal Bridge into place in New Jersey’s Hackensack River.
In many cases, the company has invented the hydraulic jacking equipment and other processes to move the items into place.
“The answer is never ‘no’ and never an automatic ‘yes,’ ” said Rick Bohne, commercial development director for Mammoet USA. “There’s always a way. Sometimes it’s a matter of whether the customer can afford it.”
Next up: Moving the new, 22 million-pound Commercial Street Bridge into place on the Parkway East in the next few weeks — the largest, heaviest bridge the Pennsylvania Department of Transportation has ever moved into place.
Read More
Beginning on water
Mammoet traces its history back to 1807, when Jan Goedkoop bought a 140-ton cargo vessel.
Goedkoop Brothers initially focused on freight and passenger movement, but it bought its first tugboat in 1862 and concentrated on tug and salvage services until it merged with another company in 1971 to form Mammoet Transport and a year later acquired another company that specialized in heavy lifting.
There have been a series of mergers and acquisitions since then, and Mammoet has grown into a worldwide company 7,000 employees strong that is best known for moving big, heavy things.
“We can move incredibly heavy things,” Bohne said “It’s the planning, the engineering, the intention. That routine makes the impossible possible.”

Here are three examples of the detail and innovation that allow Mammoet to do what it does best:
• In 2016, after helping to cut the main reactor shell at Chernobyl into three massive pieces and hauling them away, Mammoet developed a new type of hydraulic jack and special skid shoes to move the safe confinement shelter to the reactor.
This was no small item: It was 511 feet long, 853 feet wide, 360 feet tall and weighed 36,300 tons.
Mammoet created a remote-controlled system for the 116 Teflon skid shoes with an average capacity of 700 tons each to slide the shelter smoothly into place.
• In 2021, Mammoet designed a new system of hydraulic jacks to lift Russia’s Kursk nuclear submarine 354 feet from the bottom of the Barents Sea.
With a lead time of only three months, Mammoet engineers created 3,000 tons of new equipment to lift the sub, which was 377 feet long and weighed 26,000 tons.
• Beginning in 2024, Mammoet met the challenge of moving three segments of the North Portal Bridge into place on the Hackensack River.
It floated the segments to the site, then used its proprietary “Mega Jack system” to lift the 400-foot sections into place.

At times, Bohne said, the company has spent several years preparing plans for a project only for it to be canceled due to cost or a change of plans by the client.
Projects in the water are particularly challenging, Bohne said, because in addition to the heavy lift, the equipment must adjust to waves and other unexpected movement. Usually, the company uses especially sensitive shocks to absorb the movement and keep the material as stable as possible.
“If you don’t get it there the way it started out, what good is it?” he said. “The thing that we’re moving has to get there in good shape.”
Mammoet’s goal on every project is to analyze, engineer and plan so well that the result is “boring,” Bohne said.
“Routine is relative,” he said. “What we do is routine for Mammoet, but it’s not routine for the client.”
Commercial Street
Mammoet’s history will play a large part in how it moves the new Commercial Street Bridge into place.
To begin with, the company has worked here before. In 2019, Mammoet moved two 70-foot sections of the Shaler Street Bridge from a staging area to their position above Saw Mill Run Boulevard using proprietary self-propelled modular transports to carry them across the highway.
For Commercial Street, general contractor S&B Fay USA has spent nearly two years assembling the new 846-foot bridge on the floor of Frick Park beside the existing bridge, located on the Parkway East just outside the outbound Squirrel Hill Tunnel.
The plan is to close the highway at 9 p.m. Friday, raze the existing bridge, remove the rubble and slide the new bridge about 102 feet into place on the existing bridge abutments.
Fay and Mammoet have 25 days to complete the $95 million bridge-replacement project and reopen the highway or face penalties.
So how will Mammoet actually move the bridge?
Bohne stressed that it takes much more than brute force. The highly engineered process, developed over nearly two years, builds on the company’s decades of similar work.
After carefully designing the plan, Mammoet shipped about 40 containers to Pittsburgh from the Netherlands with the special materials needed to make the project work. They include 42 hydraulic jacks and special skid shoes — essentially tracks for the bridge to slide on — and a remote control system that are almost identical to the elements the company used to move the confinement shelter at Chernybol.
About three weeks ago, Mammoet’s team arrived to oversee the process of placing the equipment for the big move. Some of the jacks, each about the size of a desk, were placed at each end of the bridge but more were positioned on the bridge’s two arches because those areas carry more weight.
Bohne said crews were pleased with how well the jacks meshed with the bridge itself.
“This system is incredibly low profile — it’s short,” he said. “When they put things in place, it’s almost like it was made just for this project.”
The skid shoes are the most important element, Bohne said, because they can allow the bridge to move six ways — forward, backward, up, down, and sideways.
“These shoes are designed for a much bigger capacity,” about three times the weight of the bridge, Bohne said. “These shoes are barely going to notice this load.”
When it’s time for the move, it will be a very slow process that will take 24 to 30 hours. The jacks are designed to move the bridge 3 feet at a time — not a jarring shift, but an almost undetectable slide — then they must be reset for the next 3-foot movement.
While this is going on, all 42 jacks are monitored from the control room and drones and surveyors will be deployed to make sure the bridge is moving evenly and there is no twisting along the way, said John Myler, PennDOT’s assistant construction engineer for District 11 who is overseeing the project.
“We’re going to be monitoring as it’s moving,” he said. “We have survey points all over it to make sure it’s not wracking or twisting, and so it’s going to be a very slow process as we creep along slowly and safely to make sure we get the bridge over to the permanent location.”
‘No turning back’
Bohne said this may not be among the biggest and heaviest bridge Mammoet has moved, but what makes this project special is the precise timing.
The Parkway East averages about 100,000 vehicles a day, but the closure was set for July because PennDOT determined that is the least busy time of the year. The closure is set for 25 days, and although there could be some flexibility if something unexpected happens, the company will do everything it can to keep to that schedule.
That’s why, when Mammoet came in for a one-day test run two weeks ago, officials decided to add a second day of testing to make sure systems are as ready as possible before the move occurs.
“We want to make sure this is all sound and certainly functioning before we get into the full closure.” Myler said. “’So crews just had to make a couple adjustments, and so we said, ‘Let’s do another run to make sure everything’s in place and functioning properly.’
“With all this specialized equipment, we’re just making sure everything’s functioning the way we want, and certainly prepared prior to the closure. … We have the flexibility to take our time and be cautious. Once the bridge is gone, there’s no turning back. We want to make sure that this is ready to move as soon as we have the opportunity to move it.”
That schedule is what make this project special, Bohne said.
“This project has a heightened sense of impact,” Bohne said. “They cannot afford for this to go any way but correctly.”
Jason Zang, PennDOT’s district executive for Allegheny, Beaver and Lawrence counties, put it more succinctly at a news conference at the construction site two weeks ago.
“Make no mistake: This bridge is going to slide into place whether it likes it or not.”