Pittsburgh Regional Transit is preparing to install five bright red bus lanes in Downtown next week, which the agency anticipates will cause some temporary traffic disruptions.

The new bus lanes are a part of PRT’s ongoing University Line project, which will create a 6-mile transit corridor for buses from Downtown through Uptown and Oakland.

Some changes will be permanent, though: Bus routes 61A, 61B, 61C, and 71B will travel inbound on Fifth Avenue and outbound on Sixth Avenue when the lanes are complete, and all other traffic will do the opposite.

“Dedicated bus lanes are a major step toward improving bus service and reducing congestion. This highly anticipated upgrade is set to transform daily commutes and make public transit more reliable for thousands of riders,” PRT Director of Public Relations Melissa Rubin said in a release.

Advertise with us

The bus lanes will be installed in five phases, each accompanied by traffic changes, between May 19 and May 27:

Phase 1: May 19 at 8 p.m. to May 20 at 6 a.m.

• A bus lane will be installed on Liberty Avenue between Fifth and Sixth Avenues in the inbound direction.

• Sixth Avenue between Liberty Avenue and Wood Street will be closed.

• Buses will not stop at Liberty and Sixth Avenue (K&L Gates) and Sixth and Smithfield (Trinity Cathedral).

Phase 2: May 20 at 8 p.m. to May 21 at 8 p.m.

• A bus lane will be installed on Sixth Avenue between Grant Street and Centre Avenue in the eastbound direction.

Advertise with us

• The outbound travel lane adjacent to Mellon Green will be closed.

• Bus service will not be affected.

Phase 3: Beginning May 21 at 7 a.m.

• A bus lane will be installed on Sixth Avenue between Wood Street and Grant Street in the eastbound direction.

• Traffic will be restricted outbound on Sixth Avenue between Liberty Avenue and Grant Street. Traffic can travel inbound on Sixth Avenue between Grant Street and Wood Street.

• Buses will not stop at Sixth Avenue and Smithfield Street (Trinity Cathedral).

Advertise with us

• This phase is expected to be completed by the end of the week.

Phase 4: May 27 at 7 a.m. to May 28 (Time TBD)

• A bus lane will be installed on Fifth Avenue between Grant Street and Liberty Avenue in the westbound direction.

• A bus lane will be installed inbound on Fifth Avenue between Grant Street and Market Street. All other traffic will travel outbound in that stretch.

• Buses will not stop at the following locations on Fifth Avenue during this time: William Penn Place, Smithfield Street, Wood Street (The Goddard School), and McMasters Way.

Phase 5: Beginning May 28 at 7 a.m.

• A bus lane will be installed on Fifth Avenue between Sixth Avenue and Grant Street in the westbound direction.

Advertise with us

• A bus lane will be installed inbound on Fifth Avenue between Grant Street and Market Street.

• Traffic may travel inbound on Fifth Avenue between Market Street and Liberty Avenue and outbound on Fifth Avenue between Market Street and Grant Street.

• This phase is expected to be completed by the end of the week.