Roadway improvement work on Route 8/Butler Street will result in lane restrictions and detours through the end of October, PennDOT officials said Tuesday.
One lane will be closed between the 62nd Street Bridge and Baker Street from 9 a.m. to 3 p.m. and from 7 p.m. to 5 a.m. on weeknights through late October for milling, resurfacing, retaining wall repairs, and a new travel lane barrier, PennDOT District 11 spokesman Steve Cowan said.
The closure will most likely lead to single-lane alternating traffic, Mr. Cowan said.
One lane will be closed in each direction during the same times between Route 28 and Saxonburg Boulevard for pavement restoration and preservation work on two support structures.
Most of the construction will take place outside of peak travel hours, but commuters should expect at least three instances of one-way detours on 62nd Street Bridge, a weekend detour at the intersection of Saxonburg Boulevard and Route 8, and a detour to reconstruct the ramp carrying southbound traffic on Route 28 to northbound on Route 8.
The construction is part of a $9.14 million dollar project that began in August of 2024 with drainage inlet improvements along Butler Street. Work is expected to conclude by the end of 2025.