Pittsburgh Regional Transit announced Friday that two major light-rail projects will begin in January.

According the release, portions of the Downtown system will be closed for about two months starting Jan. 2 for replacement of the plinth, the concrete that supports the tracks.

From Jan. 2 to early February, rail service from the South Hills will end at First Avenue Station. Shuttle buses will operate every 10 minutes between First Avenue and Steel Plaza while a “Subway Local” rail car will operate every 15 minutes between Steel Plaza and the Allegheny stations on the North Side.

The release said the  contractor will halt work to accommodate any yet-to-be scheduled Steelers games at Acrisure Stadium.

Advertise with us

From early February to early March, the system will be closed between Steel Plaza and Gateway stations. Wood Street Station will not be in service.

Service from the South Hills will end at Penn Station, the normally inactive light-rail station along the Martin Luther King Jr. East Busway near The Pennsylvanian.

Shuttle buses will operate every 10 minutes between Penn Station and Gateway Station while a “Subway Local” rail car operates every 10 minutes between Gateway and Allegheny stations.

Work is also planned on the rails in the South Hills, a project known as rail grinding.

According to the release, “This critical maintenance work restores the profile of the rail by removing defects using a special machine to bring the rail to a uniform standard. A fundamental part of rail maintenance programs, rail grinding not only extends rail life but also reduces wear on the rail car wheels and improves ride quality.”

Advertise with us

Rail grinding will start the first or second week of the year and continue into March. The work will be conducted on weekdays during the day, although some overnight and weekend work will be required, PRT said.

Rail grinding will occur in sections: From South Hills Village to Washington Junction; from Washington Junction to Willow; from Willow to South Hills Junction; and, if time permits, from Washington Junction to Library Station.

Rail cars will be single-tracking through those areas so no station will be taken out of service completely.