“It’s a lucky year,” said Dave Donati, a contractor of 50 years who has worked on more than 30 projects for Pittsburgh Regional Transit.

Luck being, completing the $20 million Red Line project on time, one of several projects that make up a $150 million rehabilitation of Pittsburgh’s light rail over the next five years. Red Line construction began on June 16, and remains on track to finish by the end of August.

That’s a lot of hot days on the job.

“There’s never any shade on the railroad,” said Duane Sheets, superintendent contractor for Clarion-based Delta Contractors & Design, during a near-90-degree day in early July.

Advertise with us

“These guys are out here working in heat, humidity, noise, dirt,” said Bob Bielski, the project’s construction manager. “You’re going to go home and find dirt on your clothes you didn’t know was there. These guys live that.”

A recent night shift spent jackhammering the concrete and excavating rail, timber ties and ballasts led the following morning to starting to put it all back — with new materials. The previous track, dating to the 1980s, was well worn from 40 years of steel-on-steel wear.

After finishing repairs along Willow Avenue, Mr. Donati and his team moved on to Alfred Street at the end of June, working in 10-hour shifts to complete each side of the track running through Mt. Lebanon — one after the other to maintain single-track service. Alfred Street construction ended on July 15.

Riders across Pittsburgh have groaned over the shutdown, specifically in the South Hills, where many rely on light rail to get to Downtown. But this summer’s Red Line project is where the greatest need for repair is, said Greg O’Hare, the project’s chief engineer.

“We understand it’s a challenge,” Mr. O’Hare said. “Nobody likes to shut down the rail line.”

Advertise with us

Projects like these are for “preventative maintenance,” no different than replacing oil in a car, he said.

“If you don't change oil every 3,000 to 5,000 miles, or whatever it is, the car is not going to last. And the same thing goes for the transit side. If you don't repair the infrastructure … it's going to be problematic in the future.”

Mr. O’Hare said rail can last between 20-40 years, and curved areas are often the priority because of a higher degree of wear.

The roads are still closed at the Mt. Lebanon T station on Thursday, July 18, 2024. Two lines are working again. (Lucy Schaly / Pittsburgh Post-Gazette)

On curves along the Red Line, guarded rail will now be installed — a new system for PRT that adds another rail rather than a strap guard to keep the wheel on the track, creating a gap for the wheel to run through as it moves around a curve. It’ll wear differently and last longer, Mr. O’Hare said, and it made sense to change to the system now, although it has been standard throughout the U.S. for years.

“It wouldn’t make sense to replace this arbitrarily before it was ready to be replaced — that's not really a good use of taxpayers’ money,” he said.

Advertise with us

PRT always considers doing adjacent work while closing an area, Mr. O’Hare said, in hopes of minimizing impact to customers in the long term. On the Panhandle Bridge, which carries the T over the Monongahela River, work will be done to the bridge alongside replacing the rail, one of the projects slated for 2026.

“A lot of effort and forethought was put into the planning of this,” Mr. O’Hare said. “It may be inconvenient for a short period of time, unfortunately, but hopefully when we’re done, it will be open and be reliable for a long time to come.”

“It’s like the old saying goes: temporary inconvenience, permanent improvement,” Mr. Donati said.

The alternative can be much worse.

Saw Mill Run Boulevard Bridge was closed for months in 2022 after ice caused it to shift several inches, according to KDKA, shutting down the Red Line during a cold winter. In a crunch, PRT relied on bus operators to work overtime but it still didn’t have enough for reliable shuttles.

Advertise with us

“When that happened with the bridge, people would go to work and then couldn't get home because there was no bus shuttle at the end of the day,” Mr. O’Hare said. “I couldn't even imagine just literally being stranded and not being able to get home afterwards.”

“State of good repair” projects are intended to maintain reliability of the T before it comes to a head, and PRT has to scramble in an emergency, he said.

“If you reply upon reacting rather than preparing, the cost to react to emergencies is so much more,” Mr. O’Hare said. “It can be a total disruption of the customers. … By getting out in advance and preparing these things ahead of time, hopefully [we’re] preventing those reliability issues.”

Since June, contractors have been hard at work along the Red Line. Steel saws cut through track to mark the start and end to the curve being replaced — typically 39-foot sections, Mr. O’Hare said. The next project will start on the Mount Washington transit tunnel following the summer months.

There are growing pains for everyone with a large-scale project and new contractors, Mr. Bielski said, but the field work is going great.

Advertise with us

“It’s like a chess game: There are so many pieces moving all the time,” he said. “It’s an entire system. It takes cooperation between everyone.”

Replacing rail cars is extremely expensive, said PRT spokesman Adam Brandolph, so tracks are the first step.

“You can have the most up-to-date and efficient rail cars, but if your tracks are not up to snuff then it doesn’t matter,” he said.

Since rail is the most efficient way to get from the South Hills to Downtown, the question then becomes what to do while it’s closed.

PRT communications specialist Andrew Carr said internal planning and coordination has been paramount for the project, including public meetings, social media updates, signs plastered to each station and audio announcements. Temporary shuttles have been added to third-party apps and some buses have been made fare-free to help inconvenienced riders.

Advertise with us

“The next best option may not be a little bit less convenient,” Mr. O’Hare said. “It may be a lot less convenient for some folks, but it is much better than the alternative of not having an emergency plan.”

NOTE: This post has been updated from the original to correct the spelling of Greg O'Hare’s name.