WASHINGTON — So how did the Fern Hollow Bridge reopen only 11 months after it collapsed?

Cheryl Moon-Sirianni, executive deputy secretary of the Pennsylvania Department of Transportation, answered it in one word: Trust.

“You’re going to hear the word trust a lot,” Ms. Moon-Sirianni said Tuesday at a Capitol Hill event sponsored by the American Road and Transportation Builders Association.

The National Transportation Safety Board still is investigating the cause of the January 2022 collapse of the 447-foot-long bridge, which carries Forbes Avenue over Frick Park and is owned and maintained by the City of Pittsburgh. The span was rated in poor condition. Ten people were hurt but there were no fatalities.

Advertise with us

The $25.3 million to build a new bridge came from an emergency fund created under President Joe Biden’s bipartisan infrastructure law, so that was one hurdle quickly overcome. The bridge collapsed on the day Mr. Biden came to Pittsburgh to highlight the law.

As the rebuilding began, there was trust that the city, state and federal governments would be able to work together and come up with a plan to quickly replace the bridge. Trust that steps would be taken to protect the environment. Trust that the private companies receiving no-bid contracts to design and build the new span would provide a fair price and great work. 

“We learned a lot about how to work together,” said Ms. Moon-Sirianni, who was head of the PennDOT district that covers Pittsburgh. “We got to common ground pretty quickly.”

Declaring a disaster emergency allowed the governments and their contractor to cut through the red tape that usually is a years-long wait for approval of a new construction project. There wasn’t enough time to get the steel needed for a majestic span to replace the collapsed bridge, so they made do with concrete beams. The fabricator changed its schedule to speed up manufacturing the beams. 

“How fast do you want to have the bridge open?” said Andrew Swank, president of Swank Construction Co. of  New Kensington, which built the new bridge with design firm HDR, which has offices Downtown. “The answer to that question dictates a lot of the answers.”

Advertise with us

Because of the existing historic watchtower, nearby cemetery and the adjacent community, they couldn’t widen the bridge. And that helped because Swank had been working on a similar sized bridge and had the equipment nearby.

“The industry takes it as a challenge to complete jobs like this,“ Mr. Swank said. “What would have taken months upon months was done in one or two months.”

And as the beams came down the road to be put into place, the community was there to applaud, he said.

“We normally don’t get cheered,” Ms. Moon-Sirianni said. “They lined the streets of Pittsburgh as these bridge beams came in.” 

Jonathan D. Salant: jsalant@post-gazette.com, @JDSalant