This article was updated at 3:50 p.m. on Wednesday, Aug. 24, 2022.
The northbound ramp from the Highland Park Bridge to Route 28 will reopen at 6 p.m. Wednesday.
The ramp, which closed March 28 as part of a $47.3 million reconfiguration of the interchange, was supposed to reopen in late June. That had to be pushed back, the Pennsylvania Department of transportation said, after contractors discovered that metal straps used to stabilize a retaining wall had deteriorated and needed to be replaced.
Reopening that ramp will allow traffic from the Pittsburgh side of the bridge to flow directly onto Route 28. While the ramp was closed, traffic was detoured onto Freeport Road, which created substantial backups during evening rush hours.
The connection to northbound Route 28 is reopening only days before the next ramp closes. The ramp from the bridge to Sharpsburg will close Monday morning.
There will be additional closures, including the ramps from the bridge to Route 28 south and to Freeport Road, as the project continues through August 2023.
Golden Triangle Construction is adding separate exit lanes from Route 28 to the bridge in each direction. When the project is done, there will be two lanes of free-flowing traffic from Pittsburgh’s North Side to Kittanning.
Ed Blazina: eblazina@post-gazette.com, 412-263-1470 or on Twitter @EdBlazina.







Comments