The first pre-stressed concrete I-beams are to be delivered on Monday for construction of the new Fern Hollow Bridge.
The Pennsylvania Department of Transportation warned Thursday that delivery of the 21 beams from Roaring Spring, Blair County, to the Squirrel Hill area could cause some traffic headaches. That’s because the beams are 150 feet long, eight feet high, four feet wide and weigh 100 tons.
The beams are part of the emergency effort to replace Fern Hollow, a span on Forbes Avenue that joined Squirrel Hill and Point Breeze before it collapsed into Frick Park on Jan. 28.
The beams are being manufactured at PennStress, a division of the MacInnis Group LLC. The first beam will leave Roaring Spring at 7 a.m. Monday for the 124-mile trip to the Squirrel Hill side of the bridge.
PennDOT said there could be rolling closures on bridges as the beam is carried through Blair, Cambria and Armstrong counties on its way to Allegheny County.
Locally, the beam will travel south on Route 28 to the Veterans Bridge, cross the bridge to the Boulevard of the Allies and follow the boulevard to Forbes. Once it reaches the city, police officers will escort it to Forbes and South Dallas avenues.
Plans are to deliver two beams a day on weekdays only with the first 14 going to the Squirrel Hill side of the structure. The other seven will be delivered to the Point Breeze side of the bridge at South Braddock Avenue and Forbes, but the full route using the Parkway East and South Braddock Avenue hasn’t been determined yet.
The state received a $25.3 million discretionary grant from the Federal Highway Administration to replace the bridge, which before the pandemic carried 44,000 vehicles daily.
Although the bridge was owned by Pittsburgh, PennDOT is overseeing the project because it has more experience with emergency construction. After the emergency declaration, PennDOT hired Swank Construction Co. to begin early construction while international design firm HDR is still finishing the final design of the new structure.
Ten people were injured when the bridge collapsed about 6:45 a.m., taking a Pittsburgh Regional Transit bus and several other vehicles into the valley below it. The National Transportation Safety Board is continuing to investigate the cause of the collapse.
Ed Blazina: eblazina@post-gazette.com, 412-263-1470 0r on Twitter @EdBlazina.







Comments
Welcome to Post-Gazette subscriber-only commenting community. Please review our community guidelines.